Where the power comes from · 2025

Connecticut

Natural gas made 56% of the electricity generated in Connecticut in 2025, the 9th highest natural gas share of any state. In 2005, coal made 12% of it; in 2025, 0%.

Generated43.8 TWh2025 · 34th of 51
Capacity11 GWNameplate, September 2026
Power plants186With a generator of 1 MW or more
Renewable4%Of generation · US 24%

The mix

Connecticut's electricity by source

Share of utility-scale generation each year, 1990–2025. Hover a year for every source.

CoalOtherNuclearSolarNatural gasHydro
0%25%50%75%100%19901995200020052010201520202025Natural gas56%Nuclear38%
CoalOtherNuclearSolarNatural gasHydro
0%25%50%75%100%1990200020102020

Every plant

Connecticut's power plants

186 plants with a generator of 1 MW or more, sized by capacity and colored by main source, as of September 2026. Click one to open it.

Capacity by source

  • Natural gas5.4 GW49%
  • Other2.7 GW24%
  • Nuclear2.3 GW21%
  • Solar502 MW4.6%
  • Hydro118 MW1.1%
  • Storage33 MW0.3%
  • Wind5.0 MW<0.1%

Built and retired

What came online, what shut down

Nameplate capacity that entered service (above the line) and retired (below) in Connecticut, by year. 2026 runs through September 2026.

HydroNatural gasWindSolarStorageOtherCoal
-1 GW-500 MW0500 MW1 GW2 GW20052010201520202025Built ↑Retired ↓
HydroNatural gasWindSolarStorageOtherCoal
-1 GW-500 MW0500 MW1 GW2 GW20052010201520202025Built ↑Retired ↓

Carbon

CO₂ for every megawatt-hour

Connecticut's power plants emitted 246 kg of CO₂ for each MWh they generated in 2024, against 348 kg in 2005: the 12th lowest of 51. 11 million metric tons in all.

02004006008001,00019901991199219931994199519961997199819992000200120022003200420052006200720082009201020112012201320142015201620172018201920202021202220232024Connecticut 246US 356
ConnecticutUS
02004006008001,000199420002006201220182024246356

Connecticut among the states

  1. Generation43.8 TWh34th
  2. Renewable share4%51st
  3. Carbon-free share42%28th
  4. Cleanest electricity (kg CO₂/MWh, 2024)24612th
  5. Natural gas share56%9th
  6. Nuclear share38%7th
  7. Other share3.1%14th
  8. Solar share1.5%39th
All state rankings →

Plants

The largest plants in Connecticut

By nameplate capacity, with 2025 generation and capacity factor: generation over the most the plant could make running flat out all year.

PlantSourceCountyCapacityGeneratedCapacity factorSince
Millstone Nuclear New London 2.3 GW 17 TWh 84% 1975
CPV Towantic Energy Center Natural gas New Haven 842 MW 4.8 TWh 65% 2018
Lake Road Generating Plant Natural gas Windham 840 MW 5.8 TWh 79% 2002
Middletown Oil Middlesex 786 MW 87 GWh 1% 1958
Kleen Energy Systems Natural gas Middlesex 693 MW 3.2 TWh 53% 2011
New Haven Steam Oil New Haven 642 MW 106 GWh 2% 1975
Milford Power Project Natural gas New Haven 578 MW 3.4 TWh 67% 2004
Bridgeport Station Natural gas Fairfield 576 MW 3.4 TWh 67% 2019
Bridgeport Energy Project Natural gas Fairfield 520 MW 2.4 TWh 53% 1998
Montville Station Oil New London 495 MW 133 GWh 3% 1954
Wallingford Energy Natural gas New Haven 350 MW 107 GWh 4% 2001
GenConn Middletown LLC Oil Middlesex 242 MW 6.5 GWh 0% 2011
GenConn Devon LLC Oil New Haven 242 MW 15 GWh 1% 2010
Devon Station Oil New Haven 223 MW -1.4 GWh – 1985
Gravel Pit Solar, LLC Solar Hartford 120 MW 147 GWh – 2025
Cos Cob Oil Fairfield 115 MW 1.6 GWh 0% 1969
Waterbury Generation Natural gas New Haven 96 MW 55 GWh 7% 2009
A L Pierce Natural gas New Haven 84 MW 0.0 GWh – 2007
Algonquin Windsor Locks Natural gas Hartford 71 MW 138 GWh 22% 1990
Waterside Power, LLC Oil Fairfield 70 MW 2.0 GWh 0% 2004

Coming next

Planned projects

The largest generators reported as planned in Connecticut, by expected year. Plans change; some will be delayed or cancelled.

ProjectSourceCountyCapacityExpected
Elevate Middletown Storage Middlesex 275 MW 2027
Broadleaf Solar Solar Hartford 200 MW 2028
Pure Hedge LLC Solar Windham 70 MW 2027
KCE CT 1, LLC Storage Windham 45 MW 2031
Pure Hedge LLC Storage Windham 20 MW 2027
Groton Flanders Road Landfill Solar New London 5.0 MW 2027
Putnam Meadow Solar Station Solar Windham 4.0 MW 2027
Plainfield Solar One Solar Windham 4.0 MW 2027
CT Airport Authority Solar One Solar Hartford 4.0 MW 2027
Willington Solar One, LLC Solar Tolland 2.0 MW 2027
Windsor Locks Solar Hartford 1.8 MW 2026

Shut down

Retired since 2010

The largest generators retired in Connecticut since 2010.

PlantSourceCapacityRetired
Bridgeport Station Coal 400 MW 2021
AES Thames Coal 214 MW 2012
NRG Norwalk Harbor Oil 163 MW 2013
NRG Norwalk Harbor Oil 163 MW 2013
Bridgeport Station Oil 163 MW 2014
CT Resource Rec Authority Facility Biomass 45 MW 2022
CT Resource Rec Authority Facility Biomass 45 MW 2022
South Meadow Oil 42 MW 2023
South Meadow Oil 42 MW 2023
South Meadow Oil 42 MW 2023
South Meadow Oil 42 MW 2023
Capitol District Energy Center Natural gas 40 MW 2021

Sources: U.S. Energy Information Administration: state historical generation tables (1990–2025), Form EIA-860M generator inventory (September 2026) and Form EIA-923 plant generation. Shares leave out pumped storage. Rooftop solar is not included. Methodology.