Hydro power plant · Fairfield, CT

Stevenson

Stevenson is a 31 MW hydro power plant in Fairfield County, Connecticut, operated by FirstLight Power Resources Services LLC. Its oldest generator still running came online in 1919. In 2025 it generated 71 GWh, about what 8,400 average Connecticut homes use in a year.

Capacity31 MWNameplate, September 2026
Generated71 GWhIn 2025
Capacity factor27%Share of the most it could make, 2025
Generators4Oldest from 1919

Stevenson in context

Among the 13 hydro plants in Connecticut in the EIA's inventory, it is the 2nd largest, about 26% of the state's 116 MW of hydro capacity.

Fairfield County has 17 power plants of 1 MW or more with 1.4 GW in all; Stevenson is 2% of that and the largest of 2 hydro plants there.

Its capacity factor of 27% in 2025 is lower than the 34% typical for hydro plants across the US.

The average electricity customer in Fairfield County goes 11 hours a year without power, the 3rd most of 8 counties in Connecticut. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

05010015020020182019202020212022202320242025GWh 71
050100150200201920212023202571

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Stevenson (outlined) and other plants in Fairfield County, shaded. 41.383, -73.171.

Plant facts

Operator
FirstLight Power Resources Services LLC
Sector
IPP Non-CHP
Grid operator
ISNE
County
Fairfield County, CT
EIA plant ID
553
Where Connecticut's power comes from → Connecticut power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
4 Conventional Hydroelectric 8.0 MW 1936 –
1 Conventional Hydroelectric 7.5 MW 1919 –
2 Conventional Hydroelectric 7.5 MW 1919 –
3 Conventional Hydroelectric 7.5 MW 1919 –

Questions

Stevenson, answered

How much power does Stevenson produce?

Stevenson has 31 MW of capacity from 4 generators. In 2025 it generated 71 GWh, 27% of the most it could have made running flat out all year (its capacity factor).

How many homes does Stevenson power?

Its 2025 output of 71 GWh equals the yearly electricity use of about 8,400 average Connecticut homes (704 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Stevenson?

Stevenson is in Fairfield County, Connecticut, at about 41.383°, -73.171°. It is one of 17 power plants of 1 MW or more in the county. The average electricity customer in Fairfield County goes 11 hours a year without power, the 3rd most of 8 counties in Connecticut. The county's page has the full outage record.

Who operates Stevenson?

It is operated by FirstLight Power Resources Services LLC (EIA sector: IPP Non-CHP), and it feeds ISO New England.

When did Stevenson open?

Its oldest generator still running came online in 1919.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Connecticut home's 704 kWh a month in 2025. Methodology.