Storage power plant · Litchfield, CT
Rocky River (CT)
Rocky River (CT) is a 31 MW storage power plant in Litchfield County, Connecticut, operated by FirstLight Power Resources Services LLC. Its oldest generator still running came online in 1928.
Rocky River (CT) in context
Litchfield County has 17 power plants of 1 MW or more with 171 MW in all; Rocky River (CT) is 18% of that.
The average electricity customer in Litchfield County goes 13 hours a year without power, the 1st most of 8 counties in Connecticut. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923. Storage uses more energy charging than it returns, so its net figure is negative.
Where it is
Rocky River (CT) (outlined) and other plants in Litchfield County, shaded. 41.583, -73.435.
Plant facts
- Operator
- FirstLight Power Resources Services LLC
- Sector
- IPP Non-CHP
- Grid operator
- ISNE
- County
- Litchfield County, CT
- EIA plant ID
- 539
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 3 | Hydroelectric Pumped Storage | 24 MW | 1928 | – |
| 2 | Hydroelectric Pumped Storage | 3.5 MW | 1928 | – |
| 1 | Hydroelectric Pumped Storage | 3.5 MW | 1929 | – |
Nearby
Other plants in Litchfield County
Questions
Rocky River (CT), answered
How much can Rocky River (CT) store and deliver?
Rocky River (CT) can deliver up to 31 MW, from 3 storage units. Its net energy in 2025 was -2.4 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.
Where is Rocky River (CT)?
Rocky River (CT) is in Litchfield County, Connecticut, at about 41.583°, -73.435°. It is one of 17 power plants of 1 MW or more in the county. The average electricity customer in Litchfield County goes 13 hours a year without power, the 1st most of 8 counties in Connecticut. The county's page has the full outage record.
Who operates Rocky River (CT)?
It is operated by FirstLight Power Resources Services LLC (EIA sector: IPP Non-CHP), and it feeds ISO New England.
When did Rocky River (CT) open?
Its oldest generator still running came online in 1928.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Methodology.