Hydro power plant · New Haven, CT
Shepaug
Shepaug is a 37 MW hydro power plant in New Haven County, Connecticut, operated by FirstLight Power Resources Services LLC. Its oldest generator still running came online in 1955. In 2025 it generated 93 GWh, about what 11,000 average Connecticut homes use in a year.
Shepaug in context
Among the 13 hydro plants in Connecticut in the EIA's inventory, it is the largest, about 32% of the state's 116 MW of hydro capacity.
New Haven County has 27 power plants of 1 MW or more with 3.2 GW in all; Shepaug is 1% of that and the largest of 2 hydro plants there.
Its capacity factor of 29% in 2025 is lower than the 34% typical for hydro plants across the US.
The average electricity customer in New Haven County goes 5.7 hours a year without power, the 7th most of 8 counties in Connecticut. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Shepaug (outlined) and other plants in New Haven County, shaded. 41.448, -73.295.
Plant facts
- Operator
- FirstLight Power Resources Services LLC
- Sector
- IPP Non-CHP
- Grid operator
- ISNE
- County
- New Haven County, CT
- EIA plant ID
- 552
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Conventional Hydroelectric | 37 MW | 1955 | – |
Questions
Shepaug, answered
How much power does Shepaug produce?
Shepaug has 37 MW of capacity from one generator. In 2025 it generated 93 GWh, 29% of the most it could have made running flat out all year (its capacity factor).
How many homes does Shepaug power?
Its 2025 output of 93 GWh equals the yearly electricity use of about 11,000 average Connecticut homes (704 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Shepaug?
Shepaug is in New Haven County, Connecticut, at about 41.448°, -73.295°. It is one of 27 power plants of 1 MW or more in the county. The average electricity customer in New Haven County goes 5.7 hours a year without power, the 7th most of 8 counties in Connecticut. The county's page has the full outage record.
Who operates Shepaug?
It is operated by FirstLight Power Resources Services LLC (EIA sector: IPP Non-CHP), and it feeds ISO New England.
When did Shepaug open?
Its oldest generator still running came online in 1955.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Connecticut home's 704 kWh a month in 2025. Methodology.