Natural gas power plant · New London, CT

Generate Colchester Fuel Cells, LLC

Generate Colchester Fuel Cells, LLC is a 10 MW natural gas power plant in New London County, Connecticut, operated by Generate Colchester Fuel Cells, LLC. Its oldest generator still running came online in 2021. In 2025 it generated 72 GWh, about what 8,600 average Connecticut homes use in a year.

Capacity10 MWNameplate, September 2026
Generated72 GWhIn 2025
Capacity factor83%Share of the most it could make, 2025
Generators1Oldest from 2021

Generate Colchester Fuel Cells, LLC in context

Among the 48 natural gas plants in Connecticut in the EIA's inventory, it is the 20th largest, about 0.2% of the state's 5.0 GW of natural gas capacity.

New London County has 45 power plants of 1 MW or more with 3.0 GW in all; Generate Colchester Fuel Cells, LLC is 0% of that and the 4th largest of 9 natural gas plants there.

Its capacity factor of 83% in 2025 is higher than the 23% typical for natural gas plants across the US.

The average electricity customer in New London County goes 9.2 hours a year without power, the 5th most of 8 counties in Connecticut. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

0204060801002022202320242025GWh 72
020406080100202220232024202572

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Generate Colchester Fuel Cells, LLC (outlined) and other plants in New London County, shaded. 41.594, -72.331.

Plant facts

Operator
Generate Colchester Fuel Cells, LLC
Sector
IPP Non-CHP
Grid operator
ISNE
County
New London County, CT
EIA plant ID
66053
Where Connecticut's power comes from → Connecticut power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
GCFC Other Natural Gas 10 MW 2021 –

Questions

Generate Colchester Fuel Cells, LLC, answered

How much power does Generate Colchester Fuel Cells, LLC produce?

Generate Colchester Fuel Cells, LLC has 10 MW of capacity from one generator. In 2025 it generated 72 GWh, 83% of the most it could have made running flat out all year (its capacity factor).

How many homes does Generate Colchester Fuel Cells, LLC power?

Its 2025 output of 72 GWh equals the yearly electricity use of about 8,600 average Connecticut homes (704 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Generate Colchester Fuel Cells, LLC?

Generate Colchester Fuel Cells, LLC is in New London County, Connecticut, at about 41.594°, -72.331°. It is one of 45 power plants of 1 MW or more in the county. The average electricity customer in New London County goes 9.2 hours a year without power, the 5th most of 8 counties in Connecticut. The county's page has the full outage record.

Who operates Generate Colchester Fuel Cells, LLC?

It is operated by Generate Colchester Fuel Cells, LLC (EIA sector: IPP Non-CHP), and it feeds ISO New England.

When did Generate Colchester Fuel Cells, LLC open?

Its oldest generator still running came online in 2021.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2022–2025). Homes equivalent uses the average Connecticut home's 704 kWh a month in 2025. Methodology.