Biomass power plant · Robeson, NC
Lumberton
Lumberton is a 35 MW biomass power plant in Robeson County, North Carolina, operated by NC Renewable Power - Lumberton LLC. Its oldest generator still running came online in 1985.
Lumberton in context
Among the 71 other-fuel plants in North Carolina in the EIA's inventory, it is the 9th largest, about 3.2% of the state's 1.1 GW of other-fuel capacity.
Robeson County has 46 power plants of 1 MW or more with 419 MW in all; Lumberton is 8% of that and the 2nd largest of 3 biomass plants there.
The average electricity customer in Robeson County goes 10 hours a year without power, the 44th most of 100 counties in North Carolina. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Where it is
Lumberton (outlined) and other plants in Robeson County, shaded. 34.590, -78.997.
Plant facts
- Operator
- NC Renewable Power - Lumberton LLC
- Sector
- IPP CHP
- Grid operator
- CPLE
- County
- Robeson County, NC
- EIA plant ID
- 10382
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| GEN1 | Wood/Wood Waste Biomass | 35 MW | 1985 | – |
Nearby
Other plants in Robeson County
Questions
Lumberton, answered
How much power does Lumberton produce?
Lumberton has 35 MW of capacity from one generator. No full year of generation is reported yet.
Where is Lumberton?
Lumberton is in Robeson County, North Carolina, at about 34.590°, -78.997°. It is one of 46 power plants of 1 MW or more in the county. The average electricity customer in Robeson County goes 10 hours a year without power, the 44th most of 100 counties in North Carolina. The county's page has the full outage record.
Who operates Lumberton?
It is operated by NC Renewable Power - Lumberton LLC (EIA sector: IPP CHP), and it feeds balancing authority CPLE.
When did Lumberton open?
Its oldest generator still running came online in 1985.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Methodology.