McGrau Ford Battery Storage Facility

McGrau Ford Battery Storage Facility is a 530 MW storage power plant in Cherokee County, Georgia, operated by Georgia Power Co. Its oldest generator still running came online in 2026.

Capacity530 MWNameplate, September 2026
Net energy–Not reported
Capacity factor–Not a full year of data
Generators2Oldest from 2026

McGrau Ford Battery Storage Facility in context

Among the 6 storage plants in Georgia in the EIA's inventory, it is the 3rd largest, about 22% of the state's 2.4 GW of storage capacity.

The average electricity customer in Cherokee County goes 2.4 hours a year without power, the 141st most of 156 counties in Georgia. The county's page has the full outage record.

Where it is

McGrau Ford Battery Storage Facility (outlined) and other plants in Cherokee County, shaded. 34.325, -84.329.

Plant facts

Operator
Georgia Power Co
Sector
Electric Utility
Grid operator
SOCO
County
Cherokee County, GA
EIA plant ID
68512
Where Georgia's power comes from → Georgia power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Batteries 265 MW · 530 MWh 2026 –
2 Batteries 265 MW · 1,060 MWh 2026 –

Questions

McGrau Ford Battery Storage Facility, answered

How much can McGrau Ford Battery Storage Facility store and deliver?

McGrau Ford Battery Storage Facility can deliver up to 530 MW and hold 1,590 MWh of energy, from 2 storage units.

Where is McGrau Ford Battery Storage Facility?

McGrau Ford Battery Storage Facility is in Cherokee County, Georgia, at about 34.325°, -84.329°. The average electricity customer in Cherokee County goes 2.4 hours a year without power, the 141st most of 156 counties in Georgia. The county's page has the full outage record.

Who operates McGrau Ford Battery Storage Facility?

It is operated by Georgia Power Co (EIA sector: Electric Utility), and it feeds Southern Company.

When did McGrau Ford Battery Storage Facility open?

Its oldest generator still running came online in 2026.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Methodology.