Minco Wind IV, LLC is a 130 MW wind power plant in Canadian County, Oklahoma, operated by Minco Wind IV, LLC. Its oldest generator still running came online in 2018. In 2025 it generated 517 GWh, about what 40,000 average Oklahoma homes use in a year.
Minco Wind IV, LLC in context
Among the 70 wind plants in Oklahoma in the EIA's inventory, it is the 47th largest, about 1.0% of the state's 13 GW of wind capacity.
Canadian County has 4 power plants of 1 MW or more with 896 MW in all; Minco Wind IV, LLC is 15% of that and the 2nd largest of 2 wind plants there.
Its capacity factor of 45% in 2025 is higher than the 32% typical for wind plants across the US.
The average electricity customer in Canadian County goes 8.4 hours a year without power, the 26th most of 75 counties in Oklahoma. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Minco Wind IV, LLC (outlined) and other plants in Canadian County, shaded. 35.381, -98.270.
Plant facts
- Operator
- Minco Wind IV, LLC
- Sector
- IPP Non-CHP
- Grid operator
- SWPP
- County
- Canadian County, OK
- EIA plant ID
- 61836
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| MIV | Onshore Wind Turbine | 130 MW | 2018 | – |
Nearby
Other plants in Canadian County
Questions
Minco Wind IV, LLC, answered
How much power does Minco Wind IV, LLC produce?
Minco Wind IV, LLC has 130 MW of capacity from one generator. In 2025 it generated 517 GWh, 45% of the most it could have made running flat out all year (its capacity factor).
How many homes does Minco Wind IV, LLC power?
Its 2025 output of 517 GWh equals the yearly electricity use of about 40,000 average Oklahoma homes (1,064 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Minco Wind IV, LLC?
Minco Wind IV, LLC is in Canadian County, Oklahoma, at about 35.381°, -98.270°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Canadian County goes 8.4 hours a year without power, the 26th most of 75 counties in Oklahoma. The county's page has the full outage record.
Who operates Minco Wind IV, LLC?
It is operated by Minco Wind IV, LLC (EIA sector: IPP Non-CHP), and it feeds the Southwest Power Pool.
When did Minco Wind IV, LLC open?
Its oldest generator still running came online in 2018.