Wind power plant · Uinta, WY
Mountain Wind Power II LLC
Mountain Wind Power II LLC is a 80 MW wind power plant in Uinta County, Wyoming, operated by Mountain Wind Power II LLC. Its oldest generator still running came online in 2008. In 2025 it generated 188 GWh, about what 19,000 average Wyoming homes use in a year.
Mountain Wind Power II LLC in context
Among the 28 wind plants in Wyoming in the EIA's inventory, it is the 21st largest, about 1.7% of the state's 4.7 GW of wind capacity.
Uinta County has 3 power plants of 1 MW or more with 285 MW in all; Mountain Wind Power II LLC is 28% of that and the 2nd largest of 3 wind plants there.
Its capacity factor of 27% in 2025 is lower than the 32% typical for wind plants across the US.
The average electricity customer in Uinta County goes 0.9 hours a year without power, the 19th most of 20 counties in Wyoming. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Mountain Wind Power II LLC (outlined) and other plants in Uinta County, shaded. 41.264, -110.544.
Plant facts
- Operator
- Mountain Wind Power II LLC
- Sector
- IPP Non-CHP
- Grid operator
- PACE
- County
- Uinta County, WY
- EIA plant ID
- 56753
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Onshore Wind Turbine | 80 MW | 2008 | – |
Nearby
Other plants in Uinta County
Questions
Mountain Wind Power II LLC, answered
How much power does Mountain Wind Power II LLC produce?
Mountain Wind Power II LLC has 80 MW of capacity from one generator. In 2025 it generated 188 GWh, 27% of the most it could have made running flat out all year (its capacity factor).
How many homes does Mountain Wind Power II LLC power?
Its 2025 output of 188 GWh equals the yearly electricity use of about 19,000 average Wyoming homes (835 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Mountain Wind Power II LLC?
Mountain Wind Power II LLC is in Uinta County, Wyoming, at about 41.264°, -110.544°. It is one of 3 power plants of 1 MW or more in the county. The average electricity customer in Uinta County goes 0.9 hours a year without power, the 19th most of 20 counties in Wyoming. The county's page has the full outage record.
Who operates Mountain Wind Power II LLC?
It is operated by Mountain Wind Power II LLC (EIA sector: IPP Non-CHP), and it feeds PacifiCorp East.
When did Mountain Wind Power II LLC open?
Its oldest generator still running came online in 2008.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Wyoming home's 835 kWh a month in 2025. Methodology.