Solar power plant · Elmore, ID
Mt. Home Solar 1, LLC
Mt. Home Solar 1, LLC is a 20 MW solar power plant in Elmore County, Idaho, operated by Standard Solar. Its oldest generator still running came online in 2017. In 2025 it generated 49 GWh, about what 4,300 average Idaho homes use in a year.
Mt. Home Solar 1, LLC in context
Among the 14 solar plants in Idaho in the EIA's inventory, it is the 8th largest, about 2.4% of the state's 827 MW of solar capacity.
Elmore County has 20 power plants of 1 MW or more with 928 MW in all; Mt. Home Solar 1, LLC is 2% of that and the 3rd largest of 4 solar plants there.
Its capacity factor of 28% in 2025 is higher than the 20% typical for solar plants across the US.
The average electricity customer in Elmore County goes 3.2 hours a year without power, the 26th most of 35 counties in Idaho. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Mt. Home Solar 1, LLC (outlined) and other plants in Elmore County, shaded. 43.129, -115.752.
Plant facts
- Operator
- Standard Solar
- Sector
- IPP Non-CHP
- Grid operator
- IPCO
- County
- Elmore County, ID
- EIA plant ID
- 59695
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| MHPV1 | Solar Photovoltaic | 20 MW | 2017 | – |
Questions
Mt. Home Solar 1, LLC, answered
How much power does Mt. Home Solar 1, LLC produce?
Mt. Home Solar 1, LLC has 20 MW of capacity from one generator. In 2025 it generated 49 GWh, 28% of the most it could have made running flat out all year (its capacity factor).
How many homes does Mt. Home Solar 1, LLC power?
Its 2025 output of 49 GWh equals the yearly electricity use of about 4,300 average Idaho homes (933 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Mt. Home Solar 1, LLC?
Mt. Home Solar 1, LLC is in Elmore County, Idaho, at about 43.129°, -115.752°. It is one of 20 power plants of 1 MW or more in the county. The average electricity customer in Elmore County goes 3.2 hours a year without power, the 26th most of 35 counties in Idaho. The county's page has the full outage record.
Who operates Mt. Home Solar 1, LLC?
It is operated by Standard Solar (EIA sector: IPP Non-CHP), and it feeds Idaho Power.
When did Mt. Home Solar 1, LLC open?
Its oldest generator still running came online in 2017.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Idaho home's 933 kWh a month in 2025. Methodology.