Natural gas power plant · Wake, NC
NCSU Cates Cogeneration Plant
NCSU Cates Cogeneration Plant is a 11 MW natural gas power plant in Wake County, North Carolina, operated by NC State University, Energy Systems. Its oldest generator still running came online in 2012. In 2025 it generated 73 GWh, about what 5,800 average North Carolina homes use in a year.
NCSU Cates Cogeneration Plant in context
Among the 22 natural gas plants in North Carolina in the EIA's inventory, it is the 21st largest, about 0.1% of the state's 20 GW of natural gas capacity.
Wake County has 16 power plants of 1 MW or more with 1.1 GW in all; NCSU Cates Cogeneration Plant is 1% of that and the largest of 2 natural gas plants there.
Its capacity factor of 74% in 2025 is higher than the 23% typical for natural gas plants across the US.
The average electricity customer in Wake County goes 3.0 hours a year without power, the 94th most of 100 counties in North Carolina. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
NCSU Cates Cogeneration Plant (outlined) and other plants in Wake County, shaded. 35.784, -78.675.
Plant facts
- Operator
- NC State University, Energy Systems
- Sector
- Commercial CHP
- Grid operator
- CPLE
- County
- Wake County, NC
- EIA plant ID
- 61676
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| CTG1 | Natural Gas Fired Combustion Turbine | 5.6 MW | 2012 | – |
| CTG2 | Natural Gas Fired Combustion Turbine | 5.6 MW | 2012 | – |
Nearby
Other plants in Wake County
Questions
NCSU Cates Cogeneration Plant, answered
How much power does NCSU Cates Cogeneration Plant produce?
NCSU Cates Cogeneration Plant has 11 MW of capacity from 2 generators. In 2025 it generated 73 GWh, 74% of the most it could have made running flat out all year (its capacity factor).
How many homes does NCSU Cates Cogeneration Plant power?
Its 2025 output of 73 GWh equals the yearly electricity use of about 5,800 average North Carolina homes (1,044 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is NCSU Cates Cogeneration Plant?
NCSU Cates Cogeneration Plant is in Wake County, North Carolina, at about 35.784°, -78.675°. It is one of 16 power plants of 1 MW or more in the county. The average electricity customer in Wake County goes 3.0 hours a year without power, the 94th most of 100 counties in North Carolina. The county's page has the full outage record.
Who operates NCSU Cates Cogeneration Plant?
It is operated by NC State University, Energy Systems (EIA sector: Commercial CHP), and it feeds balancing authority CPLE.
When did NCSU Cates Cogeneration Plant open?
Its oldest generator still running came online in 2012.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average North Carolina home's 1,044 kWh a month in 2025. Methodology.