Nobles Wind Project is a 201 MW wind power plant in Nobles County, Minnesota, operated by Northern States Power Co - Minnesota. Its oldest generator still running came online in 2010. In 2025 it generated 823 GWh, about what 92,000 average Minnesota homes use in a year.

Capacity201 MWNameplate, September 2026
Generated823 GWhIn 2025
Capacity factor47%Share of the most it could make, 2025
Generators1Oldest from 2010

Nobles Wind Project in context

Among the 122 wind plants in Minnesota in the EIA's inventory, it is the 6th largest, about 4.1% of the state's 5.0 GW of wind capacity.

Nobles County has 10 power plants of 1 MW or more with 509 MW in all; Nobles Wind Project is 39% of that and the 2nd largest of 8 wind plants there.

Its capacity factor of 47% in 2025 is higher than the 32% typical for wind plants across the US.

The average electricity customer in Nobles County goes 1.9 hours a year without power. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02004006008001,00020182019202020212022202320242025GWh 823
02004006008001,0002019202120232025823

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Nobles Wind Project (outlined) and other plants in Nobles County, shaded. 43.704, -95.713.

Plant facts

Operator
Northern States Power Co - Minnesota
Sector
Electric Utility
Grid operator
MISO
County
Nobles County, MN
EIA plant ID
57047
Where Minnesota's power comes from → Minnesota power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Onshore Wind Turbine 201 MW 2010 –

Nearby

Other plants in Nobles County

Nobles 2 Wind Project · 250 MWCommunity Wind South · 30 MWWorthington · 20 MWAdrian · 2.0 MWSunset Breeze LLC · 1.3 MWMinnesota Breeze LLC · 1.3 MWG Flow Wind LLC · 1.3 MWWolf Wind Enterprises LLC · 1.3 MW

Questions

Nobles Wind Project, answered

How much power does Nobles Wind Project produce?

Nobles Wind Project has 201 MW of capacity from one generator. In 2025 it generated 823 GWh, 47% of the most it could have made running flat out all year (its capacity factor).

How many homes does Nobles Wind Project power?

Its 2025 output of 823 GWh equals the yearly electricity use of about 92,000 average Minnesota homes (743 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Nobles Wind Project?

Nobles Wind Project is in Nobles County, Minnesota, at about 43.704°, -95.713°. It is one of 10 power plants of 1 MW or more in the county. The average electricity customer in Nobles County goes 1.9 hours a year without power. The county's page has the full outage record.

Who operates Nobles Wind Project?

It is operated by Northern States Power Co - Minnesota (EIA sector: Electric Utility), and it feeds MISO.

When did Nobles Wind Project open?

Its oldest generator still running came online in 2010.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Minnesota home's 743 kWh a month in 2025. Methodology.