Wind power plant · Blair, PA

North Allegheny Windpower Project

North Allegheny Windpower Project is a 75 MW wind power plant in Blair County, Pennsylvania, operated by Deriva Energy. Its oldest generator still running came online in 2009. In 2025 it generated 218 GWh, about what 22,000 average Pennsylvania homes use in a year.

Capacity75 MWNameplate, September 2026
Generated218 GWhIn 2025
Capacity factor33%Share of the most it could make, 2025
Generators1Oldest from 2009

North Allegheny Windpower Project in context

Among the 28 wind plants in Pennsylvania in the EIA's inventory, it is the 9th largest, about 4.5% of the state's 1.7 GW of wind capacity.

Blair County has 5 power plants of 1 MW or more with 252 MW in all; North Allegheny Windpower Project is 30% of that and the 2nd largest of 4 wind plants there.

Its capacity factor of 33% in 2025 is close to the 32% typical for wind plants across the US.

The average electricity customer in Blair County goes 3.5 hours a year without power, the 58th most of 67 counties in Pennsylvania. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

05010015020025020182019202020212022202320242025GWh 218
0501001502002502019202120232025218

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

North Allegheny Windpower Project (outlined) and other plants in Blair County, shaded. 40.438, -78.544.

Plant facts

Operator
Deriva Energy
Sector
IPP Non-CHP
Grid operator
PJM
County
Blair County, PA
EIA plant ID
56651
Where Pennsylvania's power comes from → Pennsylvania power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Onshore Wind Turbine 75 MW 2009 –

Nearby

Other plants in Blair County

Questions

North Allegheny Windpower Project, answered

How much power does North Allegheny Windpower Project produce?

North Allegheny Windpower Project has 75 MW of capacity from one generator. In 2025 it generated 218 GWh, 33% of the most it could have made running flat out all year (its capacity factor).

How many homes does North Allegheny Windpower Project power?

Its 2025 output of 218 GWh equals the yearly electricity use of about 22,000 average Pennsylvania homes (839 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is North Allegheny Windpower Project?

North Allegheny Windpower Project is in Blair County, Pennsylvania, at about 40.438°, -78.544°. It is one of 5 power plants of 1 MW or more in the county. The average electricity customer in Blair County goes 3.5 hours a year without power, the 58th most of 67 counties in Pennsylvania. The county's page has the full outage record.

Who operates North Allegheny Windpower Project?

It is operated by Deriva Energy (EIA sector: IPP Non-CHP), and it feeds PJM Interconnection.

When did North Allegheny Windpower Project open?

Its oldest generator still running came online in 2009.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Pennsylvania home's 839 kWh a month in 2025. Methodology.