Natural gas power plant · Rogers, OK

Northeastern

Northeastern is a 1.5 GW natural gas power plant in Rogers County, Oklahoma, operated by Public Service Co of Oklahoma. Its oldest generator still running came online in 1961. In 2025 it generated 5.0 TWh, about what 393,000 average Oklahoma homes use in a year.

Capacity1.5 GWNameplate, September 2026
Generated5.0 TWhIn 2025
Capacity factor39%Share of the most it could make, 2025
Generators6Oldest from 1961

Northeastern in context

Among the 34 natural gas plants in Oklahoma in the EIA's inventory, it is the 4th largest, about 7.8% of the state's 19 GW of natural gas capacity.

Its capacity factor of 39% in 2025 is higher than the 23% typical for natural gas plants across the US.

The average electricity customer in Rogers County goes 4.8 hours a year without power, the 56th most of 75 counties in Oklahoma. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02,0004,0006,00020182019202020212022202320242025GWh 5,016
02,0004,0006,00020192021202320255,016

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Northeastern (outlined) and other plants in Rogers County, shaded. 36.432, -95.701.

Plant facts

Operator
Public Service Co of Oklahoma
Sector
Electric Utility
Grid operator
SWPP
County
Rogers County, OK
EIA plant ID
2963
  • Natural gas1.0 GW68%
  • Coal473 MW32%
  • Other4.5 MW0.3%
Where Oklahoma's power comes from → Oklahoma power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
2 Natural Gas Steam Turbine 473 MW 1970 –
3 Conventional Steam Coal 473 MW 1979 –
1A Natural Gas Fired Combined Cycle 179 MW 2001 –
1B Natural Gas Fired Combined Cycle 179 MW 2001 –
1 Natural Gas Fired Combined Cycle 170 MW 1961 –
IC1 Petroleum Liquids 4.5 MW 1980 –

Retired

GeneratorTechnologyCapacityOnlineRetired
4Conventional Steam Coal473 MW19802016

Questions

Northeastern, answered

How much power does Northeastern produce?

Northeastern has 1.5 GW of capacity from 6 generators. In 2025 it generated 5.0 TWh, 39% of the most it could have made running flat out all year (its capacity factor).

How many homes does Northeastern power?

Its 2025 output of 5.0 TWh equals the yearly electricity use of about 393,000 average Oklahoma homes (1,064 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Northeastern?

Northeastern is in Rogers County, Oklahoma, at about 36.432°, -95.701°. The average electricity customer in Rogers County goes 4.8 hours a year without power, the 56th most of 75 counties in Oklahoma. The county's page has the full outage record.

Who operates Northeastern?

It is operated by Public Service Co of Oklahoma (EIA sector: Electric Utility), and it feeds the Southwest Power Pool.

When did Northeastern open?

Its oldest generator still running came online in 1961.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Oklahoma home's 1,064 kWh a month in 2025. Methodology.