Hydro power plant · Union, GA
Nottely
Nottely is a 16 MW hydro power plant in Union County, Georgia, operated by Tennessee Valley Authority. Its oldest generator still running came online in 1956. In 2025 it generated 24 GWh, about what 1,900 average Georgia homes use in a year.
Nottely in context
Among the 27 hydro plants in Georgia in the EIA's inventory, it is the 18th largest, about 0.9% of the state's 1.8 GW of hydro capacity.
Its capacity factor of 17% in 2025 is lower than the 34% typical for hydro plants across the US.
The average electricity customer in Union County goes 9.8 hours a year without power, the 67th most of 156 counties in Georgia. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Nottely (outlined) and other plants in Union County, shaded. 34.959, -84.088.
Plant facts
- Operator
- Tennessee Valley Authority
- Sector
- Electric Utility
- Grid operator
- TVA
- County
- Union County, GA
- EIA plant ID
- 758
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Conventional Hydroelectric | 15 MW | 1956 | – |
| 2 | Conventional Hydroelectric | 0.9 MW | 1993 | – |
Questions
Nottely, answered
How much power does Nottely produce?
Nottely has 16 MW of capacity from 2 generators. In 2025 it generated 24 GWh, 17% of the most it could have made running flat out all year (its capacity factor).
How many homes does Nottely power?
Its 2025 output of 24 GWh equals the yearly electricity use of about 1,900 average Georgia homes (1,077 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Nottely?
Nottely is in Union County, Georgia, at about 34.959°, -84.088°. The average electricity customer in Union County goes 9.8 hours a year without power, the 67th most of 156 counties in Georgia. The county's page has the full outage record.
Who operates Nottely?
It is operated by Tennessee Valley Authority (EIA sector: Electric Utility), and it feeds the Tennessee Valley Authority.
When did Nottely open?
Its oldest generator still running came online in 1956.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Georgia home's 1,077 kWh a month in 2025. Methodology.