Solar power plant · Lake, OR
OR Solar 6, LLC
OR Solar 6, LLC is a 10 MW solar power plant in Lake County, Oregon, operated by Heelstone Energy Holdings, LLC. Its oldest generator still running came online in 2017. In 2025 it generated 22 GWh, about what 2,100 average Oregon homes use in a year.
OR Solar 6, LLC in context
Among the 151 solar plants in Oregon in the EIA's inventory, it is the 20th largest, about 0.7% of the state's 1.4 GW of solar capacity.
Lake County has 11 power plants of 1 MW or more with 125 MW in all; OR Solar 6, LLC is 8% of that and the 2nd largest of 10 solar plants there.
Its capacity factor of 25% in 2025 is higher than the 20% typical for solar plants across the US.
The average electricity customer in Lake County goes 4.3 hours a year without power, the 23rd most of 32 counties in Oregon. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
OR Solar 6, LLC (outlined) and other plants in Lake County, shaded. 42.209, -120.368.
Plant facts
- Operator
- Heelstone Energy Holdings, LLC
- Sector
- IPP Non-CHP
- Grid operator
- PACW
- County
- Lake County, OR
- EIA plant ID
- 61430
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| PV6 | Solar Photovoltaic | 10 MW | 2017 | – |
Nearby
Other plants in Lake County
Questions
OR Solar 6, LLC, answered
How much power does OR Solar 6, LLC produce?
OR Solar 6, LLC has 10 MW of capacity from one generator. In 2025 it generated 22 GWh, 25% of the most it could have made running flat out all year (its capacity factor).
How many homes does OR Solar 6, LLC power?
Its 2025 output of 22 GWh equals the yearly electricity use of about 2,100 average Oregon homes (866 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is OR Solar 6, LLC?
OR Solar 6, LLC is in Lake County, Oregon, at about 42.209°, -120.368°. It is one of 11 power plants of 1 MW or more in the county. The average electricity customer in Lake County goes 4.3 hours a year without power, the 23rd most of 32 counties in Oregon. The county's page has the full outage record.
Who operates OR Solar 6, LLC?
It is operated by Heelstone Energy Holdings, LLC (EIA sector: IPP Non-CHP), and it feeds PacifiCorp West.
When did OR Solar 6, LLC open?
Its oldest generator still running came online in 2017.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Oregon home's 866 kWh a month in 2025. Methodology.