Hydro power plant · Bonneville, ID
Palisades Dam
Palisades Dam is a 176 MW hydro power plant in Bonneville County, Idaho, operated by U S Bureau of Reclamation. Its oldest generator still running came online in 1957. In 2025 it generated 657 GWh, about what 59,000 average Idaho homes use in a year.
Palisades Dam in context
Among the 76 hydro plants in Idaho in the EIA's inventory, it is the 4th largest, about 6.5% of the state's 2.7 GW of hydro capacity.
Bonneville County has 11 power plants of 1 MW or more with 611 MW in all; Palisades Dam is 29% of that and the largest of 6 hydro plants there.
Its capacity factor of 43% in 2025 is higher than the 34% typical for hydro plants across the US.
The average electricity customer in Bonneville County goes 1.8 hours a year without power, the 32nd most of 35 counties in Idaho. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Palisades Dam (outlined) and other plants in Bonneville County, shaded. 43.335, -111.206.
Plant facts
- Operator
- U S Bureau of Reclamation
- Sector
- Electric Utility
- Grid operator
- BPAT
- County
- Bonneville County, ID
- EIA plant ID
- 850
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Conventional Hydroelectric | 44 MW | 1957 | – |
| 2 | Conventional Hydroelectric | 44 MW | 1957 | – |
| 3 | Conventional Hydroelectric | 44 MW | 1957 | – |
| 4 | Conventional Hydroelectric | 44 MW | 1958 | – |
Nearby
Other plants in Bonneville County
Questions
Palisades Dam, answered
How much power does Palisades Dam produce?
Palisades Dam has 176 MW of capacity from 4 generators. In 2025 it generated 657 GWh, 43% of the most it could have made running flat out all year (its capacity factor).
How many homes does Palisades Dam power?
Its 2025 output of 657 GWh equals the yearly electricity use of about 59,000 average Idaho homes (933 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Palisades Dam?
Palisades Dam is in Bonneville County, Idaho, at about 43.335°, -111.206°. It is one of 11 power plants of 1 MW or more in the county. The average electricity customer in Bonneville County goes 1.8 hours a year without power, the 32nd most of 35 counties in Idaho. The county's page has the full outage record.
Who operates Palisades Dam?
It is operated by U S Bureau of Reclamation (EIA sector: Electric Utility), and it feeds the Bonneville Power Administration.
When did Palisades Dam open?
Its oldest generator still running came online in 1957.