Biomass power plant · Lowndes, GA
PCA-Valdosta Mill
PCA-Valdosta Mill is a 70 MW biomass power plant in Lowndes County, Georgia, operated by PCA-Valdosta Mill. Its oldest generator still running came online in 1954. In 2025 it generated 311 GWh, about what 24,000 average Georgia homes use in a year.
PCA-Valdosta Mill in context
Among the 46 other-fuel plants in Georgia in the EIA's inventory, it is the 12th largest, about 3.0% of the state's 2.3 GW of other-fuel capacity.
Lowndes County has 10 power plants of 1 MW or more with 193 MW in all; PCA-Valdosta Mill is 36% of that and the largest of 4 biomass plants there.
Its capacity factor of 51% in 2025 is higher than the 25% typical for biomass plants across the US.
The average electricity customer in Lowndes County goes 27 hours a year without power, the 17th most of 156 counties in Georgia. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
PCA-Valdosta Mill (outlined) and other plants in Lowndes County, shaded. 30.694, -83.303.
Plant facts
- Operator
- PCA-Valdosta Mill
- Sector
- Industrial CHP
- Grid operator
- SOCO
- County
- Lowndes County, GA
- EIA plant ID
- 60084
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| TG3 | Wood/Wood Waste Biomass | 52 MW | 2011 | – |
| TG1 | Wood/Wood Waste Biomass | 10 MW | 1954 | – |
| TG2 | Wood/Wood Waste Biomass | 7.5 MW | 1954 | – |
Nearby
Other plants in Lowndes County
Questions
PCA-Valdosta Mill, answered
How much power does PCA-Valdosta Mill produce?
PCA-Valdosta Mill has 70 MW of capacity from 3 generators. In 2025 it generated 311 GWh, 51% of the most it could have made running flat out all year (its capacity factor).
How many homes does PCA-Valdosta Mill power?
Its 2025 output of 311 GWh equals the yearly electricity use of about 24,000 average Georgia homes (1,077 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is PCA-Valdosta Mill?
PCA-Valdosta Mill is in Lowndes County, Georgia, at about 30.694°, -83.303°. It is one of 10 power plants of 1 MW or more in the county. The average electricity customer in Lowndes County goes 27 hours a year without power, the 17th most of 156 counties in Georgia. The county's page has the full outage record.
Who operates PCA-Valdosta Mill?
It is operated by PCA-Valdosta Mill (EIA sector: Industrial CHP), and it feeds Southern Company.
When did PCA-Valdosta Mill open?
Its oldest generator still running came online in 1954.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Georgia home's 1,077 kWh a month in 2025. Methodology.