Solar power plant · Hopkins, TX

Pine Forest Solar I

Pine Forest Solar I is a 500 MW solar power plant in Hopkins County, Texas, operated by Pine Forest Solar I, LLC. Its oldest generator still running came online in 2025. In 2025 it generated 30 GWh, about what 2,200 average Texas homes use in a year.

Capacity500 MWNameplate, September 2026
Generated30 GWhIn 2025
Capacity factor–Not a full year of data
Generators2Oldest from 2025

Pine Forest Solar I in context

Among the 250 solar plants in Texas in the EIA's inventory, it is the 7th largest, about 1.3% of the state's 37 GW of solar capacity.

Hopkins County has 5 power plants of 1 MW or more with 1.8 GW in all; Pine Forest Solar I is 28% of that and the largest of 4 solar plants there.

The average electricity customer in Hopkins County goes 9.8 hours a year without power, the 117th most of 240 counties in Texas. The county's page has the full outage record.

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Pine Forest Solar I (outlined) and other plants in Hopkins County, shaded. 33.101, -95.392.

Plant facts

Operator
Pine Forest Solar I, LLC
Sector
IPP Non-CHP
Grid operator
DOPD
County
Hopkins County, TX
EIA plant ID
68906
  • Solar300 MW60%
  • Storage200 MW40%
Where Texas's power comes from → Texas power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
PFPV Solar Photovoltaic 300 MW 2025 –
PFBA Batteries 200 MW · 200 MWh 2025 –

Planned

GeneratorTechnologyCapacityExpected
PFBA2Batteries200 MW2027

Questions

Pine Forest Solar I, answered

How much power does Pine Forest Solar I produce?

Pine Forest Solar I has 500 MW of capacity from 2 generators. In 2025 it generated 30 GWh.

How many homes does Pine Forest Solar I power?

Its 2025 output of 30 GWh equals the yearly electricity use of about 2,200 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Pine Forest Solar I?

Pine Forest Solar I is in Hopkins County, Texas, at about 33.101°, -95.392°. It is one of 5 power plants of 1 MW or more in the county. The average electricity customer in Hopkins County goes 9.8 hours a year without power, the 117th most of 240 counties in Texas. The county's page has the full outage record.

Who operates Pine Forest Solar I?

It is operated by Pine Forest Solar I, LLC (EIA sector: IPP Non-CHP), and it feeds balancing authority DOPD.

When did Pine Forest Solar I open?

Its oldest generator still running came online in 2025. 1 more generator is planned.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.