Platinum Storage is a 348 MW storage power plant in Fannin County, Texas, operated by Platinum Energy Storage LLC. Its oldest generator still running came online in 2026.

Capacity348 MWNameplate, September 2026
Net energy–Not reported
Capacity factor–Not a full year of data
Generators1Oldest from 2026

Platinum Storage in context

Among the 233 storage plants in Texas in the EIA's inventory, it is the 2nd largest, about 2.1% of the state's 16 GW of storage capacity.

Fannin County has 4 power plants of 1 MW or more with 565 MW in all; Platinum Storage is 62% of that.

The average electricity customer in Fannin County goes 7.1 hours a year without power, the 165th most of 240 counties in Texas. The county's page has the full outage record.

Where it is

Platinum Storage (outlined) and other plants in Fannin County, shaded. 33.611, -96.372.

Plant facts

Operator
Platinum Energy Storage LLC
Sector
IPP Non-CHP
Grid operator
ERCO
County
Fannin County, TX
EIA plant ID
69044
Where Texas's power comes from → Texas power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
PLAT Batteries 348 MW · 298 MWh 2026 –

Questions

Platinum Storage, answered

How much can Platinum Storage store and deliver?

Platinum Storage can deliver up to 348 MW and hold 298 MWh of energy, from one battery or storage system.

Where is Platinum Storage?

Platinum Storage is in Fannin County, Texas, at about 33.611°, -96.372°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Fannin County goes 7.1 hours a year without power, the 165th most of 240 counties in Texas. The county's page has the full outage record.

Who operates Platinum Storage?

It is operated by Platinum Energy Storage LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.

When did Platinum Storage open?

Its oldest generator still running came online in 2026.