Wind power plant · Kingfisher, OK

Red Dirt Wind Project

Red Dirt Wind Project is a 299 MW wind power plant in Kingfisher County, Oklahoma, operated by Red Dirt Wind Project, LLC. Its oldest generator still running came online in 2017. In 2025 it generated 778 GWh, about what 61,000 average Oklahoma homes use in a year.

Capacity299 MWNameplate, September 2026
Generated778 GWhIn 2025
Capacity factor30%Share of the most it could make, 2025
Generators1Oldest from 2017

Red Dirt Wind Project in context

Among the 70 wind plants in Oklahoma in the EIA's inventory, it is the 9th largest, about 2.2% of the state's 13 GW of wind capacity.

Kingfisher County has 3 power plants of 1 MW or more with 606 MW in all; Red Dirt Wind Project is 49% of that and the largest of 2 wind plants there.

Its capacity factor of 30% in 2025 is close to the 32% typical for wind plants across the US.

The average electricity customer in Kingfisher County goes 12 hours a year without power, the 11th most of 75 counties in Oklahoma. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02004006008001,0001,20020182019202020212022202320242025GWh 778
02004006008001,0001,2002019202120232025778

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Red Dirt Wind Project (outlined) and other plants in Kingfisher County, shaded. 36.051, -97.784.

Plant facts

Operator
Red Dirt Wind Project, LLC
Sector
IPP Non-CHP
Grid operator
SWPP
County
Kingfisher County, OK
EIA plant ID
61270
Where Oklahoma's power comes from → Oklahoma power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
RDDRT Onshore Wind Turbine 299 MW 2017 –

Nearby

Other plants in Kingfisher County

Kingfisher Wind LLC · 298 MWKingfisher · 9.1 MW

Questions

Red Dirt Wind Project, answered

How much power does Red Dirt Wind Project produce?

Red Dirt Wind Project has 299 MW of capacity from one generator. In 2025 it generated 778 GWh, 30% of the most it could have made running flat out all year (its capacity factor).

How many homes does Red Dirt Wind Project power?

Its 2025 output of 778 GWh equals the yearly electricity use of about 61,000 average Oklahoma homes (1,064 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Red Dirt Wind Project?

Red Dirt Wind Project is in Kingfisher County, Oklahoma, at about 36.051°, -97.784°. It is one of 3 power plants of 1 MW or more in the county. The average electricity customer in Kingfisher County goes 12 hours a year without power, the 11th most of 75 counties in Oklahoma. The county's page has the full outage record.

Who operates Red Dirt Wind Project?

It is operated by Red Dirt Wind Project, LLC (EIA sector: IPP Non-CHP), and it feeds the Southwest Power Pool.

When did Red Dirt Wind Project open?

Its oldest generator still running came online in 2017.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Oklahoma home's 1,064 kWh a month in 2025. Methodology.