Solar power plant · San Juan, UT

Red Mesa Solar Project

Red Mesa Solar Project is a 72 MW solar power plant in San Juan County, Utah, operated by NTUA Generation - Utah, LLC. Its oldest generator still running came online in 2023. In 2025 it generated 188 GWh, about what 21,000 average Utah homes use in a year.

Capacity72 MWNameplate, September 2026
Generated188 GWhIn 2025
Capacity factor30%Share of the most it could make, 2025
Generators1Oldest from 2023

Red Mesa Solar Project in context

Among the 56 solar plants in Utah in the EIA's inventory, it is the 23rd largest, about 2.4% of the state's 3.0 GW of solar capacity.

San Juan County has 2 power plants of 1 MW or more with 134 MW in all; Red Mesa Solar Project is 54% of that.

Its capacity factor of 30% in 2025 is higher than the 20% typical for solar plants across the US.

The average electricity customer in San Juan County goes 1.9 hours a year without power, the 19th most of 23 counties in Utah. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

050100150200250202320242025GWh 188
050100150200250202320242025188

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Red Mesa Solar Project (outlined) and other plants in San Juan County, shaded. 37.121, -109.412.

Plant facts

Operator
NTUA Generation - Utah, LLC
Sector
IPP Non-CHP
Grid operator
PACE
County
San Juan County, UT
EIA plant ID
66404
Where Utah's power comes from → Utah power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
PV Solar Photovoltaic 72 MW 2023 –

Nearby

Other plants in San Juan County

Questions

Red Mesa Solar Project, answered

How much power does Red Mesa Solar Project produce?

Red Mesa Solar Project has 72 MW of capacity from one generator. In 2025 it generated 188 GWh, 30% of the most it could have made running flat out all year (its capacity factor).

How many homes does Red Mesa Solar Project power?

Its 2025 output of 188 GWh equals the yearly electricity use of about 21,000 average Utah homes (761 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Red Mesa Solar Project?

Red Mesa Solar Project is in San Juan County, Utah, at about 37.121°, -109.412°. It is one of 2 power plants of 1 MW or more in the county. The average electricity customer in San Juan County goes 1.9 hours a year without power, the 19th most of 23 counties in Utah. The county's page has the full outage record.

Who operates Red Mesa Solar Project?

It is operated by NTUA Generation - Utah, LLC (EIA sector: IPP Non-CHP), and it feeds PacifiCorp East.

When did Red Mesa Solar Project open?

Its oldest generator still running came online in 2023.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2023–2025). Homes equivalent uses the average Utah home's 761 kWh a month in 2025. Methodology.