Solar power plant · Pinal, AZ
Saint Solar
Saint Solar is a 100 MW solar power plant in Pinal County, Arizona, operated by Saint Solar LLC. Its oldest generator still running came online in 2021. In 2025 it generated 284 GWh, about what 23,000 average Arizona homes use in a year.
Saint Solar in context
Among the 109 solar plants in Arizona in the EIA's inventory, it is the 31st largest, about 1.0% of the state's 9.9 GW of solar capacity.
Pinal County has 22 power plants of 1 MW or more with 4.9 GW in all; Saint Solar is 2% of that and the 6th largest of 14 solar plants there.
Its capacity factor of 32% in 2025 is higher than the 20% typical for solar plants across the US.
The average electricity customer in Pinal County goes 1.8 hours a year without power, the 5th most of 11 counties in Arizona. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Saint Solar (outlined) and other plants in Pinal County, shaded. 32.866, -111.502.
Plant facts
- Operator
- Saint Solar LLC
- Sector
- IPP Non-CHP
- Grid operator
- SRP
- County
- Pinal County, AZ
- EIA plant ID
- 63476
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| SAINT | Solar Photovoltaic | 100 MW | 2021 | – |
Questions
Saint Solar, answered
How much power does Saint Solar produce?
Saint Solar has 100 MW of capacity from one generator. In 2025 it generated 284 GWh, 32% of the most it could have made running flat out all year (its capacity factor).
How many homes does Saint Solar power?
Its 2025 output of 284 GWh equals the yearly electricity use of about 23,000 average Arizona homes (1,030 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Saint Solar?
Saint Solar is in Pinal County, Arizona, at about 32.866°, -111.502°. It is one of 22 power plants of 1 MW or more in the county. The average electricity customer in Pinal County goes 1.8 hours a year without power, the 5th most of 11 counties in Arizona. The county's page has the full outage record.
Who operates Saint Solar?
It is operated by Saint Solar LLC (EIA sector: IPP Non-CHP), and it feeds Salt River Project.
When did Saint Solar open?
Its oldest generator still running came online in 2021.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2021–2025). Homes equivalent uses the average Arizona home's 1,030 kWh a month in 2025. Methodology.