Solar power plant · San Juan, NM

San Juan Solar I

San Juan Solar I is a 300 MW solar power plant in San Juan County, New Mexico, operated by San Juan Solar I, LLC. Its oldest generator still running came online in 2024. In 2025 it generated 485 GWh, about what 63,000 average New Mexico homes use in a year.

Capacity300 MWNameplate, September 2026
Generated485 GWhIn 2025
Capacity factor18%Share of the most it could make, 2025
Generators2Oldest from 2024

San Juan Solar I in context

Among the 111 solar plants in New Mexico in the EIA's inventory, it is the 2nd largest, about 7.9% of the state's 3.8 GW of solar capacity.

San Juan County has 4 power plants of 1 MW or more with 2.1 GW in all; San Juan Solar I is 15% of that.

Its capacity factor of 18% in 2025 is close to the 20% typical for solar plants across the US.

The average electricity customer in San Juan County goes 3.0 hours a year without power, the 13th most of 20 counties in New Mexico. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

020040060020242025GWh 485
020040060020242025485

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

San Juan Solar I (outlined) and other plants in San Juan County, shaded. 36.843, -108.351.

Plant facts

Operator
San Juan Solar I, LLC
Sector
IPP Non-CHP
Grid operator
PNM
County
San Juan County, NM
EIA plant ID
66574
  • Solar200 MW67%
  • Storage100 MW33%
Where New Mexico's power comes from → New Mexico power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
SANS Solar Photovoltaic 200 MW 2024 –
SJSS Batteries 100 MW · 561 MWh 2024 –

Nearby

Other plants in San Juan County

Questions

San Juan Solar I, answered

How much power does San Juan Solar I produce?

San Juan Solar I has 300 MW of capacity from 2 generators. In 2025 it generated 485 GWh, 18% of the most it could have made running flat out all year (its capacity factor).

How many homes does San Juan Solar I power?

Its 2025 output of 485 GWh equals the yearly electricity use of about 63,000 average New Mexico homes (638 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is San Juan Solar I?

San Juan Solar I is in San Juan County, New Mexico, at about 36.843°, -108.351°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in San Juan County goes 3.0 hours a year without power, the 13th most of 20 counties in New Mexico. The county's page has the full outage record.

Who operates San Juan Solar I?

It is operated by San Juan Solar I, LLC (EIA sector: IPP Non-CHP), and it feeds balancing authority PNM.

When did San Juan Solar I open?

Its oldest generator still running came online in 2024.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2024–2025). Homes equivalent uses the average New Mexico home's 638 kWh a month in 2025. Methodology.