Oil power plant · Santa Clara, CA
SC 1 Data Center, Phase 2
SC 1 Data Center, Phase 2 is a 100 MW oil power plant in Santa Clara County, California, operated by Xeres Ventures LLC. Its oldest generator still running came online in 2011. In 2025 it generated 0.4 GWh, about what 67 average California homes use in a year.
SC 1 Data Center, Phase 2 in context
Among the 157 other-fuel plants in California in the EIA's inventory, it is the 7th largest, about 2.0% of the state's 4.9 GW of other-fuel capacity.
Santa Clara County has 53 power plants of 1 MW or more with 1.9 GW in all; SC 1 Data Center, Phase 2 is 5% of that and the largest of 11 oil plants there.
The average electricity customer in Santa Clara County goes 4.7 hours a year without power, the 38th most of 56 counties in California. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
SC 1 Data Center, Phase 2 (outlined) and other plants in Santa Clara County, shaded. 37.362, -121.944.
Plant facts
- Operator
- Xeres Ventures LLC
- Sector
- Commercial Non-CHP
- Grid operator
- CISO
- County
- Santa Clara County, CA
- EIA plant ID
- 59074
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 14B | Petroleum Liquids | 2.3 MW | 2014 | – |
| EG10A | Petroleum Liquids | 2.3 MW | 2014 | – |
| EG10B | Petroleum Liquids | 2.3 MW | 2014 | – |
| EG11A | Petroleum Liquids | 2.3 MW | 2014 | – |
| EG11B | Petroleum Liquids | 2.3 MW | 2014 | – |
| EG12A | Petroleum Liquids | 2.3 MW | 2014 | – |
| EG12B | Petroleum Liquids | 2.3 MW | 2014 | – |
| EG13A | Petroleum Liquids | 2.3 MW | 2014 | – |
| EG13B | Petroleum Liquids | 2.3 MW | 2014 | – |
| EG14A | Petroleum Liquids | 2.3 MW | 2014 | – |
| EG9B | Petroleum Liquids | 2.3 MW | 2014 | – |
| EG15A | Petroleum Liquids | 2.3 MW | 2015 | – |
| EG15B | Petroleum Liquids | 2.3 MW | 2015 | – |
| EG16A | Petroleum Liquids | 2.3 MW | 2015 | – |
| EG16B | Petroleum Liquids | 2.3 MW | 2015 | – |
| EG9A | Petroleum Liquids | 2.3 MW | 2015 | – |
| 17A | Petroleum Liquids | 2.3 MW | 2017 | – |
| 17B | Petroleum Liquids | 2.3 MW | 2017 | – |
| 18A | Petroleum Liquids | 2.3 MW | 2017 | – |
| 18B | Petroleum Liquids | 2.3 MW | 2017 | – |
| 19A | Petroleum Liquids | 2.3 MW | 2017 | – |
| 19B | Petroleum Liquids | 2.3 MW | 2017 | – |
| 20A | Petroleum Liquids | 2.3 MW | 2017 | – |
| 20B | Petroleum Liquids | 2.3 MW | 2017 | – |
| 21A | Petroleum Liquids | 2.3 MW | 2017 | – |
| 21B | Petroleum Liquids | 2.3 MW | 2017 | – |
| 22A | Petroleum Liquids | 2.3 MW | 2017 | – |
| 22B | Petroleum Liquids | 2.3 MW | 2017 | – |
| EG1A | Petroleum Liquids | 2.2 MW | 2011 | – |
| EG1B | Petroleum Liquids | 2.2 MW | 2011 | – |
| EG2A | Petroleum Liquids | 2.2 MW | 2011 | – |
| EG2B | Petroleum Liquids | 2.2 MW | 2011 | – |
| EG3A | Petroleum Liquids | 2.2 MW | 2011 | – |
| EG3B | Petroleum Liquids | 2.2 MW | 2011 | – |
| EG4A | Petroleum Liquids | 2.2 MW | 2011 | – |
| EG4B | Petroleum Liquids | 2.2 MW | 2011 | – |
| EG5A | Petroleum Liquids | 2.2 MW | 2011 | – |
| EG5B | Petroleum Liquids | 2.2 MW | 2011 | – |
| EG6A | Petroleum Liquids | 2.2 MW | 2011 | – |
| EG6B | Petroleum Liquids | 2.2 MW | 2011 | – |
| EG7A | Petroleum Liquids | 2.2 MW | 2011 | – |
| EG7B | Petroleum Liquids | 2.2 MW | 2011 | – |
| EG8B | Petroleum Liquids | 2.2 MW | 2011 | – |
| GEN8A | Petroleum Liquids | 2.2 MW | 2020 | – |
Retired
| Generator | Technology | Capacity | Online | Retired |
|---|---|---|---|---|
| EG8A | Petroleum Liquids | 2.2 MW | 2011 | 2020 |
Nearby
Other plants in Santa Clara County
Questions
SC 1 Data Center, Phase 2, answered
How much power does SC 1 Data Center, Phase 2 produce?
SC 1 Data Center, Phase 2 has 100 MW of capacity from 44 generators. In 2025 it generated 0.4 GWh, 0% of the most it could have made running flat out all year (its capacity factor).
How many homes does SC 1 Data Center, Phase 2 power?
Its 2025 output of 0.4 GWh equals the yearly electricity use of about 67 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is SC 1 Data Center, Phase 2?
SC 1 Data Center, Phase 2 is in Santa Clara County, California, at about 37.362°, -121.944°. It is one of 53 power plants of 1 MW or more in the county. The average electricity customer in Santa Clara County goes 4.7 hours a year without power, the 38th most of 56 counties in California. The county's page has the full outage record.
Who operates SC 1 Data Center, Phase 2?
It is operated by Xeres Ventures LLC (EIA sector: Commercial Non-CHP), and it feeds the California ISO.
When did SC 1 Data Center, Phase 2 open?
Its oldest generator still running came online in 2011.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.