Wind power plant · Floyd, TX

South Plains Wind Phase I

South Plains Wind Phase I is a 200 MW wind power plant in Floyd County, Texas, operated by Evergreen Wind, LLC. Its oldest generator still running came online in 2015. In 2025 it generated 677 GWh, about what 51,000 average Texas homes use in a year.

Capacity200 MWNameplate, September 2026
Generated677 GWhIn 2025
Capacity factor39%Share of the most it could make, 2025
Generators1Oldest from 2015

South Plains Wind Phase I in context

Among the 230 wind plants in Texas in the EIA's inventory, it is the 106th largest, about 0.4% of the state's 45 GW of wind capacity.

Floyd County has 5 power plants of 1 MW or more with 761 MW in all; South Plains Wind Phase I is 26% of that and the 2nd largest of 5 wind plants there.

Its capacity factor of 39% in 2025 is higher than the 32% typical for wind plants across the US.

The average electricity customer in Floyd County goes 6.7 hours a year without power, the 173rd most of 240 counties in Texas. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02004006008001,00020182019202020212022202320242025GWh 677
02004006008001,0002019202120232025677

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

South Plains Wind Phase I (outlined) and other plants in Floyd County, shaded. 34.081, -101.324.

Plant facts

Operator
Evergreen Wind, LLC
Sector
IPP Non-CHP
Grid operator
ERCO
County
Floyd County, TX
EIA plant ID
59384
Where Texas's power comes from → Texas power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Onshore Wind Turbine 200 MW 2015 –

Questions

South Plains Wind Phase I, answered

How much power does South Plains Wind Phase I produce?

South Plains Wind Phase I has 200 MW of capacity from one generator. In 2025 it generated 677 GWh, 39% of the most it could have made running flat out all year (its capacity factor).

How many homes does South Plains Wind Phase I power?

Its 2025 output of 677 GWh equals the yearly electricity use of about 51,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is South Plains Wind Phase I?

South Plains Wind Phase I is in Floyd County, Texas, at about 34.081°, -101.324°. It is one of 5 power plants of 1 MW or more in the county. The average electricity customer in Floyd County goes 6.7 hours a year without power, the 173rd most of 240 counties in Texas. The county's page has the full outage record.

Who operates South Plains Wind Phase I?

It is operated by Evergreen Wind, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.

When did South Plains Wind Phase I open?

Its oldest generator still running came online in 2015.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.