Solar power plant · Jeff Davis, GA

SR Snipesville II

SR Snipesville II is a 107 MW solar power plant in Jeff Davis County, Georgia, operated by SR Snipesville II, LLC. Its oldest generator still running came online in 2021. In 2025 it generated 250 GWh, about what 19,000 average Georgia homes use in a year.

Capacity107 MWNameplate, September 2026
Generated250 GWhIn 2025
Capacity factor27%Share of the most it could make, 2025
Generators1Oldest from 2021

SR Snipesville II in context

Among the 154 solar plants in Georgia in the EIA's inventory, it is the 16th largest, about 1.9% of the state's 5.8 GW of solar capacity.

Jeff Davis County has 6 power plants of 1 MW or more with 413 MW in all; SR Snipesville II is 26% of that and the largest of 6 solar plants there.

Its capacity factor of 27% in 2025 is higher than the 20% typical for solar plants across the US.

The average electricity customer in Jeff Davis County goes 45 hours a year without power, the 2nd most of 156 counties in Georgia. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

010020030020212022202320242025GWh 250
010020030020212022202320242025250

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

SR Snipesville II (outlined) and other plants in Jeff Davis County, shaded. 31.709, -82.716.

Plant facts

Operator
SR Snipesville II, LLC
Sector
IPP Non-CHP
Grid operator
SOCO
County
Jeff Davis County, GA
EIA plant ID
65376
Where Georgia's power comes from → Georgia power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
SNIP2 Solar Photovoltaic 107 MW 2021 –

Questions

SR Snipesville II, answered

How much power does SR Snipesville II produce?

SR Snipesville II has 107 MW of capacity from one generator. In 2025 it generated 250 GWh, 27% of the most it could have made running flat out all year (its capacity factor).

How many homes does SR Snipesville II power?

Its 2025 output of 250 GWh equals the yearly electricity use of about 19,000 average Georgia homes (1,077 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is SR Snipesville II?

SR Snipesville II is in Jeff Davis County, Georgia, at about 31.709°, -82.716°. It is one of 6 power plants of 1 MW or more in the county. The average electricity customer in Jeff Davis County goes 45 hours a year without power, the 2nd most of 156 counties in Georgia. The county's page has the full outage record.

Who operates SR Snipesville II?

It is operated by SR Snipesville II, LLC (EIA sector: IPP Non-CHP), and it feeds Southern Company.

When did SR Snipesville II open?

Its oldest generator still running came online in 2021.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2021–2025). Homes equivalent uses the average Georgia home's 1,077 kWh a month in 2025. Methodology.