Stanislaus is a 82 MW hydro power plant in Tuolumne County, California, operated by Pacific Gas & Electric Co.. Its oldest generator still running came online in 1963. In 2025 it generated 200 GWh, about what 34,000 average California homes use in a year.
Stanislaus in context
Among the 238 hydro plants in California in the EIA's inventory, it is the 40th largest, about 0.8% of the state's 10 GW of hydro capacity.
Tuolumne County has 20 power plants of 1 MW or more with 1.2 GW in all; Stanislaus is 7% of that and the 6th largest of 15 hydro plants there.
Its capacity factor of 28% in 2025 is lower than the 34% typical for hydro plants across the US.
The average electricity customer in Tuolumne County goes 59 hours a year without power, the 5th most of 56 counties in California. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Stanislaus (outlined) and other plants in Tuolumne County, shaded. 38.139, -120.370.
Plant facts
- Operator
- Pacific Gas & Electric Co.
- Sector
- Electric Utility
- Grid operator
- CISO
- County
- Tuolumne County, CA
- EIA plant ID
- 285
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| HC1 | Conventional Hydroelectric | 82 MW | 1963 | – |
Questions
Stanislaus, answered
How much power does Stanislaus produce?
Stanislaus has 82 MW of capacity from one generator. In 2025 it generated 200 GWh, 28% of the most it could have made running flat out all year (its capacity factor).
How many homes does Stanislaus power?
Its 2025 output of 200 GWh equals the yearly electricity use of about 34,000 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Stanislaus?
Stanislaus is in Tuolumne County, California, at about 38.139°, -120.370°. It is one of 20 power plants of 1 MW or more in the county. The average electricity customer in Tuolumne County goes 59 hours a year without power, the 5th most of 56 counties in California. The county's page has the full outage record.
Who operates Stanislaus?
It is operated by Pacific Gas & Electric Co. (EIA sector: Electric Utility), and it feeds the California ISO.
When did Stanislaus open?
Its oldest generator still running came online in 1963.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.