Wind power plant · Santa Barbara, CA

Strauss Wind Farm

Strauss Wind Farm is a 95 MW wind power plant in Santa Barbara County, California, operated by Strauss Wind LLC. Its oldest generator still running came online in 2023. In 2025 it generated 224 GWh, about what 38,000 average California homes use in a year.

Capacity95 MWNameplate, September 2026
Generated224 GWhIn 2025
Capacity factor27%Share of the most it could make, 2025
Generators1Oldest from 2023

Strauss Wind Farm in context

Among the 112 wind plants in California in the EIA's inventory, it is the 30th largest, about 1.4% of the state's 6.6 GW of wind capacity.

Santa Barbara County has 13 power plants of 1 MW or more with 363 MW in all; Strauss Wind Farm is 26% of that.

Its capacity factor of 27% in 2025 is lower than the 32% typical for wind plants across the US.

The average electricity customer in Santa Barbara County goes 5.6 hours a year without power, the 36th most of 56 counties in California. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

0100200300202320242025GWh 224
0100200300202320242025224

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Strauss Wind Farm (outlined) and other plants in Santa Barbara County, shaded. 34.580, -120.564.

Plant facts

Operator
Strauss Wind LLC
Sector
IPP Non-CHP
Grid operator
CISO
County
Santa Barbara County, CA
EIA plant ID
62113
Where California's power comes from → California power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
ST-CA Onshore Wind Turbine 95 MW 2023 –

Questions

Strauss Wind Farm, answered

How much power does Strauss Wind Farm produce?

Strauss Wind Farm has 95 MW of capacity from one generator. In 2025 it generated 224 GWh, 27% of the most it could have made running flat out all year (its capacity factor).

How many homes does Strauss Wind Farm power?

Its 2025 output of 224 GWh equals the yearly electricity use of about 38,000 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Strauss Wind Farm?

Strauss Wind Farm is in Santa Barbara County, California, at about 34.580°, -120.564°. It is one of 13 power plants of 1 MW or more in the county. The average electricity customer in Santa Barbara County goes 5.6 hours a year without power, the 36th most of 56 counties in California. The county's page has the full outage record.

Who operates Strauss Wind Farm?

It is operated by Strauss Wind LLC (EIA sector: IPP Non-CHP), and it feeds the California ISO.

When did Strauss Wind Farm open?

Its oldest generator still running came online in 2023.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2023–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.