Wind power plant · Nolan, TX

Sweetwater Wind 4 LLC

Sweetwater Wind 4 LLC is a 241 MW wind power plant in Nolan County, Texas, operated by Leeward Asset Management, LLC. Its oldest generator still running came online in 2007. In 2025 it generated 633 GWh, about what 48,000 average Texas homes use in a year.

Capacity241 MWNameplate, September 2026
Generated633 GWhIn 2025
Capacity factor30%Share of the most it could make, 2025
Generators1Oldest from 2007

Sweetwater Wind 4 LLC in context

Among the 230 wind plants in Texas in the EIA's inventory, it is the 57th largest, about 0.5% of the state's 45 GW of wind capacity.

Nolan County has 17 power plants of 1 MW or more with 2.8 GW in all; Sweetwater Wind 4 LLC is 9% of that and the 2nd largest of 15 wind plants there.

Its capacity factor of 30% in 2025 is close to the 32% typical for wind plants across the US.

The average electricity customer in Nolan County goes 7.9 hours a year without power, the 149th most of 240 counties in Texas. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

020040060080020182019202020212022202320242025GWh 633
02004006008002019202120232025633

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Sweetwater Wind 4 LLC (outlined) and other plants in Nolan County, shaded. 32.312, -100.530.

Plant facts

Operator
Leeward Asset Management, LLC
Sector
IPP Non-CHP
Grid operator
ERCO
County
Nolan County, TX
EIA plant ID
56337
Where Texas's power comes from → Texas power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
SW4 Onshore Wind Turbine 241 MW 2007 –

Questions

Sweetwater Wind 4 LLC, answered

How much power does Sweetwater Wind 4 LLC produce?

Sweetwater Wind 4 LLC has 241 MW of capacity from one generator. In 2025 it generated 633 GWh, 30% of the most it could have made running flat out all year (its capacity factor).

How many homes does Sweetwater Wind 4 LLC power?

Its 2025 output of 633 GWh equals the yearly electricity use of about 48,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Sweetwater Wind 4 LLC?

Sweetwater Wind 4 LLC is in Nolan County, Texas, at about 32.312°, -100.530°. It is one of 17 power plants of 1 MW or more in the county. The average electricity customer in Nolan County goes 7.9 hours a year without power, the 149th most of 240 counties in Texas. The county's page has the full outage record.

Who operates Sweetwater Wind 4 LLC?

It is operated by Leeward Asset Management, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.

When did Sweetwater Wind 4 LLC open?

Its oldest generator still running came online in 2007.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.