Wind power plant · Dewey, OK

Taloga Wind LLC

Taloga Wind LLC is a 130 MW wind power plant in Dewey County, Oklahoma, operated by Taloga Wind LLC. Its oldest generator still running came online in 2011. In 2025 it generated 188 GWh, about what 15,000 average Oklahoma homes use in a year.

Capacity130 MWNameplate, September 2026
Generated188 GWhIn 2025
Capacity factor17%Share of the most it could make, 2025
Generators1Oldest from 2011

Taloga Wind LLC in context

Among the 70 wind plants in Oklahoma in the EIA's inventory, it is the 46th largest, about 1.0% of the state's 13 GW of wind capacity.

Dewey County has 5 power plants of 1 MW or more with 881 MW in all; Taloga Wind LLC is 15% of that and the 4th largest of 5 wind plants there.

Its capacity factor of 17% in 2025 is lower than the 32% typical for wind plants across the US.

The average electricity customer in Dewey County goes 20 hours a year without power, the 3rd most of 75 counties in Oklahoma. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

010020030040050020182019202020212022202320242025GWh 188
01002003004005002019202120232025188

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Taloga Wind LLC (outlined) and other plants in Dewey County, shaded. 35.856, -98.968.

Plant facts

Operator
Taloga Wind LLC
Sector
IPP Non-CHP
Grid operator
SWPP
County
Dewey County, OK
EIA plant ID
57261
Where Oklahoma's power comes from → Oklahoma power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Onshore Wind Turbine 130 MW 2011 –

Questions

Taloga Wind LLC, answered

How much power does Taloga Wind LLC produce?

Taloga Wind LLC has 130 MW of capacity from one generator. In 2025 it generated 188 GWh, 17% of the most it could have made running flat out all year (its capacity factor).

How many homes does Taloga Wind LLC power?

Its 2025 output of 188 GWh equals the yearly electricity use of about 15,000 average Oklahoma homes (1,064 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Taloga Wind LLC?

Taloga Wind LLC is in Dewey County, Oklahoma, at about 35.856°, -98.968°. It is one of 5 power plants of 1 MW or more in the county. The average electricity customer in Dewey County goes 20 hours a year without power, the 3rd most of 75 counties in Oklahoma. The county's page has the full outage record.

Who operates Taloga Wind LLC?

It is operated by Taloga Wind LLC (EIA sector: IPP Non-CHP), and it feeds the Southwest Power Pool.

When did Taloga Wind LLC open?

Its oldest generator still running came online in 2011.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Oklahoma home's 1,064 kWh a month in 2025. Methodology.