Solar power plant · Malheur, OR

Thunderegg Solar Center, LLC

Thunderegg Solar Center, LLC is a 10 MW solar power plant in Malheur County, Oregon, operated by Cypress Creek Renewables. Its oldest generator still running came online in 2016. In 2025 it generated 20 GWh, about what 2,000 average Oregon homes use in a year.

Capacity10 MWNameplate, September 2026
Generated20 GWhIn 2025
Capacity factor23%Share of the most it could make, 2025
Generators1Oldest from 2016

Thunderegg Solar Center, LLC in context

Among the 151 solar plants in Oregon in the EIA's inventory, it is the 13th largest, about 0.7% of the state's 1.4 GW of solar capacity.

Malheur County has 14 power plants of 1 MW or more with 110 MW in all; Thunderegg Solar Center, LLC is 9% of that and the 2nd largest of 10 solar plants there.

Its capacity factor of 23% in 2025 is close to the 20% typical for solar plants across the US.

The average electricity customer in Malheur County goes 2.5 hours a year without power, the 29th most of 32 counties in Oregon. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

051015202520182019202020212022202320242025GWh 20
0510152025201920212023202520

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Thunderegg Solar Center, LLC (outlined) and other plants in Malheur County, shaded. 43.931, -116.988.

Plant facts

Operator
Cypress Creek Renewables
Sector
IPP Non-CHP
Grid operator
IPCO
County
Malheur County, OR
EIA plant ID
60334
Where Oregon's power comes from → Oregon power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
TSC1 Solar Photovoltaic 10 MW 2016 –

Nearby

Other plants in Malheur County

Neal Hot Springs Geothermal Project · 33 MWOpen Range Solar Center, LLC · 10 MWVale Air Solar Center, LLC · 10 MWHyline Solar Center, LLC · 9.0 MWTunnel 1 Power Project · 8.5 MWGrove Solar Center, LLC · 6.0 MWOwyhee Dam Power Project · 5.0 MWRailroad Solar Center, LLC · 4.5 MW

Questions

Thunderegg Solar Center, LLC, answered

How much power does Thunderegg Solar Center, LLC produce?

Thunderegg Solar Center, LLC has 10 MW of capacity from one generator. In 2025 it generated 20 GWh, 23% of the most it could have made running flat out all year (its capacity factor).

How many homes does Thunderegg Solar Center, LLC power?

Its 2025 output of 20 GWh equals the yearly electricity use of about 2,000 average Oregon homes (866 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Thunderegg Solar Center, LLC?

Thunderegg Solar Center, LLC is in Malheur County, Oregon, at about 43.931°, -116.988°. It is one of 14 power plants of 1 MW or more in the county. The average electricity customer in Malheur County goes 2.5 hours a year without power, the 29th most of 32 counties in Oregon. The county's page has the full outage record.

Who operates Thunderegg Solar Center, LLC?

It is operated by Cypress Creek Renewables (EIA sector: IPP Non-CHP), and it feeds Idaho Power.

When did Thunderegg Solar Center, LLC open?

Its oldest generator still running came online in 2016.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Oregon home's 866 kWh a month in 2025. Methodology.