Hydro power plant · Montgomery, NC

Tillery

Tillery is a 84 MW hydro power plant in Montgomery County, North Carolina, operated by Duke Energy Progress - (NC). Its oldest generator still running came online in 1928. In 2025 it generated 118 GWh, about what 9,400 average North Carolina homes use in a year.

Capacity84 MWNameplate, September 2026
Generated118 GWhIn 2025
Capacity factor16%Share of the most it could make, 2025
Generators4Oldest from 1928

Tillery in context

Among the 37 hydro plants in North Carolina in the EIA's inventory, it is the 8th largest, about 4.7% of the state's 1.8 GW of hydro capacity.

Montgomery County has 13 power plants of 1 MW or more with 261 MW in all; Tillery is 32% of that and the largest of 2 hydro plants there.

Its capacity factor of 16% in 2025 is lower than the 34% typical for hydro plants across the US.

The average electricity customer in Montgomery County goes 13 hours a year without power, the 32nd most of 100 counties in North Carolina. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

010020030040020182019202020212022202320242025GWh 118
01002003004002019202120232025118

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Tillery (outlined) and other plants in Montgomery County, shaded. 35.207, -80.065.

Plant facts

Operator
Duke Energy Progress - (NC)
Sector
Electric Utility
Grid operator
CPLE
County
Montgomery County, NC
EIA plant ID
2714
Where North Carolina's power comes from → North Carolina power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Conventional Hydroelectric 22 MW 1928 –
3 Conventional Hydroelectric 22 MW 1928 –
4 Conventional Hydroelectric 22 MW 1960 –
2 Conventional Hydroelectric 18 MW 1928 –

Nearby

Other plants in Montgomery County

Cabin Creek Solar, LLC · 70 MWTuckertown Hydro · 42 MWMontgomery Solar LLC · 20 MWUwharrie Mountain Renewable · 9.6 MWBiscoe Solar LLC · 5.0 MWHector Farm · 5.0 MWAchilles Solar · 5.0 MWKalish Farm Solar · 5.0 MW

Questions

Tillery, answered

How much power does Tillery produce?

Tillery has 84 MW of capacity from 4 generators. In 2025 it generated 118 GWh, 16% of the most it could have made running flat out all year (its capacity factor).

How many homes does Tillery power?

Its 2025 output of 118 GWh equals the yearly electricity use of about 9,400 average North Carolina homes (1,044 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Tillery?

Tillery is in Montgomery County, North Carolina, at about 35.207°, -80.065°. It is one of 13 power plants of 1 MW or more in the county. The average electricity customer in Montgomery County goes 13 hours a year without power, the 32nd most of 100 counties in North Carolina. The county's page has the full outage record.

Who operates Tillery?

It is operated by Duke Energy Progress - (NC) (EIA sector: Electric Utility), and it feeds balancing authority CPLE.

When did Tillery open?

Its oldest generator still running came online in 1928.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average North Carolina home's 1,044 kWh a month in 2025. Methodology.