Tillery is a 84 MW hydro power plant in Montgomery County, North Carolina, operated by Duke Energy Progress - (NC). Its oldest generator still running came online in 1928. In 2025 it generated 118 GWh, about what 9,400 average North Carolina homes use in a year.
Tillery in context
Among the 37 hydro plants in North Carolina in the EIA's inventory, it is the 8th largest, about 4.7% of the state's 1.8 GW of hydro capacity.
Montgomery County has 13 power plants of 1 MW or more with 261 MW in all; Tillery is 32% of that and the largest of 2 hydro plants there.
Its capacity factor of 16% in 2025 is lower than the 34% typical for hydro plants across the US.
The average electricity customer in Montgomery County goes 13 hours a year without power, the 32nd most of 100 counties in North Carolina. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Tillery (outlined) and other plants in Montgomery County, shaded. 35.207, -80.065.
Plant facts
- Operator
- Duke Energy Progress - (NC)
- Sector
- Electric Utility
- Grid operator
- CPLE
- County
- Montgomery County, NC
- EIA plant ID
- 2714
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Conventional Hydroelectric | 22 MW | 1928 | – |
| 3 | Conventional Hydroelectric | 22 MW | 1928 | – |
| 4 | Conventional Hydroelectric | 22 MW | 1960 | – |
| 2 | Conventional Hydroelectric | 18 MW | 1928 | – |
Nearby
Other plants in Montgomery County
Questions
Tillery, answered
How much power does Tillery produce?
Tillery has 84 MW of capacity from 4 generators. In 2025 it generated 118 GWh, 16% of the most it could have made running flat out all year (its capacity factor).
How many homes does Tillery power?
Its 2025 output of 118 GWh equals the yearly electricity use of about 9,400 average North Carolina homes (1,044 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Tillery?
Tillery is in Montgomery County, North Carolina, at about 35.207°, -80.065°. It is one of 13 power plants of 1 MW or more in the county. The average electricity customer in Montgomery County goes 13 hours a year without power, the 32nd most of 100 counties in North Carolina. The county's page has the full outage record.
Who operates Tillery?
It is operated by Duke Energy Progress - (NC) (EIA sector: Electric Utility), and it feeds balancing authority CPLE.
When did Tillery open?
Its oldest generator still running came online in 1928.