Storage power plant · Washington, AR

Westside Wastewater Treatment Plant Hybr

Westside Wastewater Treatment Plant Hybr is a 11 MW storage power plant in Washington County, Arkansas, operated by Today's Power, Inc.. Its oldest generator still running came online in 2019. In 2025 it generated 2.8 GWh, about what 217 average Arkansas homes use in a year.

Capacity11 MWNameplate, September 2026
Net energy2.8 GWhIn 2025
Capacity factor–Not a full year of data
Generators2Oldest from 2019

Westside Wastewater Treatment Plant Hybr in context

Among the 4 storage plants in Arkansas in the EIA's inventory, it is the 2nd largest, about 35% of the state's 31 MW of storage capacity.

Washington County has 10 power plants of 1 MW or more with 454 MW in all; Westside Wastewater Treatment Plant Hybr is 2% of that and the 2nd largest of 2 storage plants there.

The average electricity customer in Washington County goes 2.5 hours a year without power, the 70th most of 73 counties in Arkansas. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923. Storage uses more energy charging than it returns, so its net figure is negative.

0246810122019202020212022202320242025GWh 3
02468101220192021202320253

Where it is

Westside Wastewater Treatment Plant Hybr (outlined) and other plants in Washington County, shaded. 36.041, -94.140.

Plant facts

Operator
Today's Power, Inc.
Sector
Commercial Non-CHP
Grid operator
SWPP
County
Washington County, AR
EIA plant ID
62683
  • Storage6.0 MW55%
  • Solar5.0 MW45%
Where Arkansas's power comes from → Arkansas power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
FAYWB Batteries 6.0 MW · 13 MWh 2019 –
FAYW1 Solar Photovoltaic 5.0 MW 2019 –

Nearby

Other plants in Washington County

Harry D Mattison Gas Plant · 349 MWElkins Generating Center · 66 MWNoland Wastewater Treatment Plant Hybrid · 11 MWUA Central Utility Plant · 5.6 MWWaste Management Eco Vista LFGTE · 4.0 MWSpringdale School District · 2.9 MWOzark Solar Park · 2.4 MWOzarks Natural Energy Community Solar · 1.0 MW

Questions

Westside Wastewater Treatment Plant Hybr, answered

How much can Westside Wastewater Treatment Plant Hybr store and deliver?

Westside Wastewater Treatment Plant Hybr can deliver up to 11 MW and hold 13 MWh of energy, from 2 storage units. Its net energy in 2025 was 2.8 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.

Where is Westside Wastewater Treatment Plant Hybr?

Westside Wastewater Treatment Plant Hybr is in Washington County, Arkansas, at about 36.041°, -94.140°. It is one of 10 power plants of 1 MW or more in the county. The average electricity customer in Washington County goes 2.5 hours a year without power, the 70th most of 73 counties in Arkansas. The county's page has the full outage record.

Who operates Westside Wastewater Treatment Plant Hybr?

It is operated by Today's Power, Inc. (EIA sector: Commercial Non-CHP), and it feeds the Southwest Power Pool.

When did Westside Wastewater Treatment Plant Hybr open?

Its oldest generator still running came online in 2019.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2019–2025). Homes equivalent uses the average Arkansas home's 1,076 kWh a month in 2025. Methodology.