Solar power plant · Wilson, NC
Wilson Solar Farm 4
Wilson Solar Farm 4 is a 10 MW solar power plant in Wilson County, North Carolina, operated by Headwater Energy, LLC. Its oldest generator still running came online in 2017. In 2025 it generated 14 GWh, about what 1,100 average North Carolina homes use in a year.
Wilson Solar Farm 4 in context
Among the 756 solar plants in North Carolina in the EIA's inventory, it is the 99th largest, about 0.1% of the state's 7.1 GW of solar capacity.
Wilson County has 15 power plants of 1 MW or more with 151 MW in all; Wilson Solar Farm 4 is 7% of that and the 3rd largest of 13 solar plants there.
Its capacity factor of 16% in 2025 is lower than the 20% typical for solar plants across the US.
The average electricity customer in Wilson County goes 1.9 hours a year without power, the 97th most of 100 counties in North Carolina. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Wilson Solar Farm 4 (outlined) and other plants in Wilson County, shaded. 35.700, -78.000.
Plant facts
- Operator
- Headwater Energy, LLC
- Sector
- IPP Non-CHP
- Grid operator
- CPLE
- County
- Wilson County, NC
- EIA plant ID
- 61277
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| WILS4 | Solar Photovoltaic | 10 MW | 2017 | – |
Nearby
Other plants in Wilson County
Questions
Wilson Solar Farm 4, answered
How much power does Wilson Solar Farm 4 produce?
Wilson Solar Farm 4 has 10 MW of capacity from one generator. In 2025 it generated 14 GWh, 16% of the most it could have made running flat out all year (its capacity factor).
How many homes does Wilson Solar Farm 4 power?
Its 2025 output of 14 GWh equals the yearly electricity use of about 1,100 average North Carolina homes (1,044 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Wilson Solar Farm 4?
Wilson Solar Farm 4 is in Wilson County, North Carolina, at about 35.700°, -78.000°. It is one of 15 power plants of 1 MW or more in the county. The average electricity customer in Wilson County goes 1.9 hours a year without power, the 97th most of 100 counties in North Carolina. The county's page has the full outage record.
Who operates Wilson Solar Farm 4?
It is operated by Headwater Energy, LLC (EIA sector: IPP Non-CHP), and it feeds balancing authority CPLE.
When did Wilson Solar Farm 4 open?
Its oldest generator still running came online in 2017.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average North Carolina home's 1,044 kWh a month in 2025. Methodology.