Storage power plant · Kaufman, TX
Ables Springs Solar & Storage
Ables Springs Solar & Storage is a 100 MW storage power plant in Kaufman County, Texas, operated by Ables Springs Solar, LLC. Its oldest generator still running came online in 2025. In 2025 it generated 310 GWh, about what 23,000 average Texas homes use in a year.
Ables Springs Solar & Storage in context
Among the 233 storage plants in Texas in the EIA's inventory, it is the 78th largest, about 0.6% of the state's 16 GW of storage capacity.
Kaufman County has 4 power plants of 1 MW or more with 2.4 GW in all; Ables Springs Solar & Storage is 4% of that.
The average electricity customer in Kaufman County goes 5.9 hours a year without power, the 183rd most of 240 counties in Texas. The county's page has the full outage record.
Where it is
Ables Springs Solar & Storage (outlined) and other plants in Kaufman County, shaded. 32.820, -96.185.
Plant facts
- Operator
- Ables Springs Solar, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Kaufman County, TX
- EIA plant ID
- 66905
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| BESS | Batteries | 100 MW · 158 MWh | 2025 | – |
Planned
| Generator | Technology | Capacity | Expected |
|---|---|---|---|
| SOLAR | Solar Photovoltaic | 151 MW | 2026 |
Nearby
Other plants in Kaufman County
Questions
Ables Springs Solar & Storage, answered
How much can Ables Springs Solar & Storage store and deliver?
Ables Springs Solar & Storage can deliver up to 100 MW and hold 158 MWh of energy, from one battery or storage system. Its net energy in 2025 was 310 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.
Where is Ables Springs Solar & Storage?
Ables Springs Solar & Storage is in Kaufman County, Texas, at about 32.820°, -96.185°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Kaufman County goes 5.9 hours a year without power, the 183rd most of 240 counties in Texas. The county's page has the full outage record.
Who operates Ables Springs Solar & Storage?
It is operated by Ables Springs Solar, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Ables Springs Solar & Storage open?
Its oldest generator still running came online in 2025. 1 more generator is planned.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.