Solar power plant · Clark, NV
Apex Solar PV Power Project
Apex Solar PV Power Project is a 20 MW solar power plant in Clark County, Nevada, operated by Southern Power Co. Its oldest generator still running came online in 2012. In 2025 it generated 48 GWh, about what 4,600 average Nevada homes use in a year.
Apex Solar PV Power Project in context
Among the 58 solar plants in Nevada in the EIA's inventory, it is the 36th largest, about 0.3% of the state's 6.2 GW of solar capacity.
Clark County has 64 power plants of 1 MW or more with 14 GW in all; Apex Solar PV Power Project is 0% of that and the 28th largest of 45 solar plants there.
Its capacity factor of 27% in 2025 is higher than the 20% typical for solar plants across the US.
The average electricity customer in Clark County goes 1.2 hours a year without power, the 12th most of 12 counties in Nevada. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Apex Solar PV Power Project (outlined) and other plants in Clark County, shaded. 36.390, -114.970.
Plant facts
- Operator
- Southern Power Co
- Sector
- IPP Non-CHP
- Grid operator
- NEVP
- County
- Clark County, NV
- EIA plant ID
- 58489
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Solar Photovoltaic | 20 MW | 2012 | – |
Questions
Apex Solar PV Power Project, answered
How much power does Apex Solar PV Power Project produce?
Apex Solar PV Power Project has 20 MW of capacity from one generator. In 2025 it generated 48 GWh, 27% of the most it could have made running flat out all year (its capacity factor).
How many homes does Apex Solar PV Power Project power?
Its 2025 output of 48 GWh equals the yearly electricity use of about 4,600 average Nevada homes (868 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Apex Solar PV Power Project?
Apex Solar PV Power Project is in Clark County, Nevada, at about 36.390°, -114.970°. It is one of 64 power plants of 1 MW or more in the county. The average electricity customer in Clark County goes 1.2 hours a year without power, the 12th most of 12 counties in Nevada. The county's page has the full outage record.
Who operates Apex Solar PV Power Project?
It is operated by Southern Power Co (EIA sector: IPP Non-CHP), and it feeds NV Energy.
When did Apex Solar PV Power Project open?
Its oldest generator still running came online in 2012.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Nevada home's 868 kWh a month in 2025. Methodology.