Wind power plant · McIntosh, ND
Badger Wind, LLC
Badger Wind, LLC is a 250 MW wind power plant in McIntosh County, North Dakota, operated by Badger Wind , LLC. Its oldest generator still running came online in 2026.
Badger Wind, LLC in context
Among the 42 wind plants in North Dakota in the EIA's inventory, it is the 2nd largest, about 5.0% of the state's 5.0 GW of wind capacity.
McIntosh County has 2 power plants of 1 MW or more with 400 MW in all; Badger Wind, LLC is 63% of that and the largest of 2 wind plants there.
The average electricity customer in McIntosh County goes 2.2 hours a year without power. The county's page has the full outage record.
Where it is
Badger Wind, LLC (outlined) and other plants in McIntosh County, shaded. 46.217, -99.598.
Plant facts
- Operator
- Badger Wind , LLC
- Sector
- IPP Non-CHP
- Grid operator
- MISO
- County
- McIntosh County, ND
- EIA plant ID
- 64342
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 5555 | Onshore Wind Turbine | 250 MW | 2026 | – |
Nearby
Other plants in McIntosh County
Questions
Badger Wind, LLC, answered
How much power does Badger Wind, LLC produce?
Badger Wind, LLC has 250 MW of capacity from one generator. No full year of generation is reported yet.
Where is Badger Wind, LLC?
Badger Wind, LLC is in McIntosh County, North Dakota, at about 46.217°, -99.598°. It is one of 2 power plants of 1 MW or more in the county. The average electricity customer in McIntosh County goes 2.2 hours a year without power. The county's page has the full outage record.
Who operates Badger Wind, LLC?
It is operated by Badger Wind , LLC (EIA sector: IPP Non-CHP), and it feeds MISO.
When did Badger Wind, LLC open?
Its oldest generator still running came online in 2026.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Methodology.