Wind power plant · Beaver, OK

Balko Wind LLC

Balko Wind LLC is a 300 MW wind power plant in Beaver County, Oklahoma, operated by Balko Wind LLC. Its oldest generator still running came online in 2015. In 2025 it generated 802 GWh, about what 63,000 average Oklahoma homes use in a year.

Capacity300 MWNameplate, September 2026
Generated802 GWhIn 2025
Capacity factor31%Share of the most it could make, 2025
Generators1Oldest from 2015

Balko Wind LLC in context

Among the 70 wind plants in Oklahoma in the EIA's inventory, it is the 8th largest, about 2.2% of the state's 13 GW of wind capacity.

Beaver County has 4 power plants of 1 MW or more with 798 MW in all; Balko Wind LLC is 38% of that and the largest of 4 wind plants there.

Its capacity factor of 31% in 2025 is close to the 32% typical for wind plants across the US.

The average electricity customer in Beaver County goes 8.4 hours a year without power, the 25th most of 75 counties in Oklahoma. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

05001,0001,50020182019202020212022202320242025GWh 802
05001,0001,5002019202120232025802

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Balko Wind LLC (outlined) and other plants in Beaver County, shaded. 36.518, -100.847.

Plant facts

Operator
Balko Wind LLC
Sector
IPP Non-CHP
Grid operator
SWPP
County
Beaver County, OK
EIA plant ID
58900
Where Oklahoma's power comes from → Oklahoma power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
BAL1 Onshore Wind Turbine 300 MW 2015 –

Questions

Balko Wind LLC, answered

How much power does Balko Wind LLC produce?

Balko Wind LLC has 300 MW of capacity from one generator. In 2025 it generated 802 GWh, 31% of the most it could have made running flat out all year (its capacity factor).

How many homes does Balko Wind LLC power?

Its 2025 output of 802 GWh equals the yearly electricity use of about 63,000 average Oklahoma homes (1,064 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Balko Wind LLC?

Balko Wind LLC is in Beaver County, Oklahoma, at about 36.518°, -100.847°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Beaver County goes 8.4 hours a year without power, the 25th most of 75 counties in Oklahoma. The county's page has the full outage record.

Who operates Balko Wind LLC?

It is operated by Balko Wind LLC (EIA sector: IPP Non-CHP), and it feeds the Southwest Power Pool.

When did Balko Wind LLC open?

Its oldest generator still running came online in 2015.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Oklahoma home's 1,064 kWh a month in 2025. Methodology.