Wind power plant · Berkshire, MA
Berkshire Wind Power Project
Berkshire Wind Power Project is a 20 MW wind power plant in Berkshire County, Massachusetts, operated by Massachusetts Mun Wholes Electric Co. Its oldest generator still running came online in 2011. In 2025 it generated 42 GWh, about what 5,900 average Massachusetts homes use in a year.
Berkshire Wind Power Project in context
Among the 20 wind plants in Massachusetts in the EIA's inventory, it is the 3rd largest, about 2.2% of the state's 899 MW of wind capacity.
Berkshire County has 42 power plants of 1 MW or more with 1.0 GW in all; Berkshire Wind Power Project is 2% of that and the 2nd largest of 4 wind plants there.
Its capacity factor of 24% in 2025 is lower than the 32% typical for wind plants across the US.
The average electricity customer in Berkshire County goes 3.3 hours a year without power, the 12th most of 14 counties in Massachusetts. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Berkshire Wind Power Project (outlined) and other plants in Berkshire County, shaded. 42.587, -73.275.
Plant facts
- Operator
- Massachusetts Mun Wholes Electric Co
- Sector
- Electric Utility
- Grid operator
- ISNE
- County
- Berkshire County, MA
- EIA plant ID
- 57721
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| BWP | Onshore Wind Turbine | 15 MW | 2011 | – |
| HN-8 | Onshore Wind Turbine | 2.3 MW | 2019 | – |
| HN-9 | Onshore Wind Turbine | 2.3 MW | 2019 | – |
Nearby
Other plants in Berkshire County
Questions
Berkshire Wind Power Project, answered
How much power does Berkshire Wind Power Project produce?
Berkshire Wind Power Project has 20 MW of capacity from 3 generators. In 2025 it generated 42 GWh, 24% of the most it could have made running flat out all year (its capacity factor).
How many homes does Berkshire Wind Power Project power?
Its 2025 output of 42 GWh equals the yearly electricity use of about 5,900 average Massachusetts homes (596 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Berkshire Wind Power Project?
Berkshire Wind Power Project is in Berkshire County, Massachusetts, at about 42.587°, -73.275°. It is one of 42 power plants of 1 MW or more in the county. The average electricity customer in Berkshire County goes 3.3 hours a year without power, the 12th most of 14 counties in Massachusetts. The county's page has the full outage record.
Who operates Berkshire Wind Power Project?
It is operated by Massachusetts Mun Wholes Electric Co (EIA sector: Electric Utility), and it feeds ISO New England.
When did Berkshire Wind Power Project open?
Its oldest generator still running came online in 2011.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Massachusetts home's 596 kWh a month in 2025. Methodology.