Where the power comes from · 2025
Massachusetts
Natural gas made 77% of the electricity generated in Massachusetts in 2025, the 3rd highest natural gas share of any state. In 2005, coal made 25% of it; in 2025, 0%.
The mix
Massachusetts's electricity by source
Share of utility-scale generation each year, 1990–2025. Hover a year for every source.
Every plant
Massachusetts's power plants
691 plants with a generator of 1 MW or more, sized by capacity and colored by main source, as of September 2026. Click one to open it.
Capacity by source
Built and retired
What came online, what shut down
Nameplate capacity that entered service (above the line) and retired (below) in Massachusetts, by year. 2026 runs through September 2026.
Carbon
CO₂ for every megawatt-hour
Massachusetts's power plants emitted 416 kg of CO₂ for each MWh they generated in 2024, against 564 kg in 2005: the 32nd lowest of 51. 8.9 million metric tons in all.
Massachusetts among the states
- Generation22.9 TWh41st
- Renewable share17%26th
- Carbon-free share17%46th
- Cleanest electricity (kg CO₂/MWh, 2024)41632nd
- Natural gas share77%3rd
- Other share9.3%6th
- Solar share9.2%13th
- Hydro share3.3%20th
More on Massachusetts
Power outage history → Rooftop solar and home batteries → Average electric bills →Plants
The largest plants in Massachusetts
By nameplate capacity, with 2025 generation and capacity factor: generation over the most the plant could make running flat out all year.
| Plant | Source | County | Capacity | Generated | Capacity factor | Since |
|---|---|---|---|---|---|---|
| Canal | Oil | Barnstable | 1.5 GW | 374 GWh | 3% | 1968 |
| Northfield Mountain | Storage | Franklin | 1.2 GW | -284.6 GWh | – | 1972 |
| Fore River Generating Station | Natural gas | Norfolk | 872 MW | 3.1 TWh | 41% | 2003 |
| Vineyard Wind 1 | Wind | Dukes | 800 MW | – | – | 2026 |
| Salem Harbor Power Development LP | Natural gas | Essex | 798 MW | 1.8 TWh | 26% | 2018 |
| Bear Swamp | Storage | Berkshire | 666 MW | -154.4 GWh | – | 1974 |
| ANP Bellingham Energy Project | Natural gas | Norfolk | 578 MW | 3.5 TWh | 69% | 2002 |
| ANP Blackstone Energy Project | Natural gas | Worcester | 578 MW | 3.3 TWh | 64% | 2001 |
| Stony Brook | Oil | Hampden | 542 MW | 104 GWh | 2% | 1981 |
| Millennium Power | Natural gas | Worcester | 428 MW | 852 GWh | 23% | 2001 |
| Bellingham Cogeneration Facility | Natural gas | Norfolk | 386 MW | 318 GWh | 9% | 1991 |
| Berkshire Power | Natural gas | Hampden | 289 MW | 810 GWh | 32% | 1999 |
| Exelon West Medway II LLC | Natural gas | Norfolk | 264 MW | 211 GWh | 9% | 2019 |
| Masspower | Natural gas | Hampden | 261 MW | 442 GWh | 19% | 1993 |
| Medway Grid | Storage | Norfolk | 250 MW | – | – | 2026 |
| Milford Power LP | Natural gas | Worcester | 249 MW | 253 GWh | 12% | 1993 |
| Kendall Square Station | Natural gas | Middlesex | 235 MW | 1.5 TWh | 75% | 1958 |
| Dighton Power Plant | Natural gas | Bristol | 200 MW | 276 GWh | 16% | 1999 |
| Pittsfield Generating LP | Natural gas | Berkshire | 176 MW | 135 GWh | 9% | 1990 |
| Cranberry Point Energy Storage | Storage | Plymouth | 150 MW | -9.6 GWh | – | 2025 |
| Exelon Medway LLC | Oil | Norfolk | 135 MW | 4.4 GWh | 0% | 1970 |
| Cleary Flood Hybrid | Natural gas | Bristol | 121 MW | 54 GWh | 5% | 1975 |
| Potter Station 2 | Natural gas | Norfolk | 116 MW | 41 GWh | 4% | 2009 |
| SEMASS Resource Recovery | Biomass | Plymouth | 99 MW | 567 GWh | 66% | 1988 |
| Dartmouth Power Associates LP | Natural gas | Bristol | 97 MW | 89 GWh | 10% | 1992 |
| Medical Area Total Energy Plant | Natural gas | Suffolk | 95 MW | 314 GWh | 38% | 1980 |
| Deer Island Treatment Plant | Oil | Suffolk | 73 MW | 33 GWh | 5% | 1995 |
| M Street Jet | Oil | Suffolk | 69 MW | 0.3 GWh | 0% | 1979 |
| MMWEC Simple Cycle Gas Turbine | Natural gas | Essex | 65 MW | 8.3 GWh | 2% | 2024 |
| Cabot | Hydro | Franklin | 62 MW | 240 GWh | 44% | 1915 |
| Wheelabrator Saugus | Biomass | Essex | 58 MW | 185 GWh | 37% | 1985 |
| Wheelabrator Millbury Facility | Biomass | Worcester | 48 MW | 319 GWh | 77% | 1987 |
| Covanta Haverhill | Biomass | Essex | 46 MW | 198 GWh | 49% | 1989 |
| Waters River | Natural gas | Essex | 44 MW | 5.5 GWh | 1% | 1990 |
| Mass Inst Tech Cntrl Utilities/Cogen Plt | Natural gas | Middlesex | 43 MW | 209 GWh | 55% | 2021 |
| Exelon Framingham LLC | Oil | Norfolk | 43 MW | 1.2 GWh | 0% | 1969 |
| Wheelabrator North Andover | Biomass | Essex | 40 MW | 240 GWh | 68% | 1985 |
| Hadley Falls | Hydro | Hampden | 33 MW | 137 GWh | 47% | 1952 |
| Cobble Mountain | Hydro | Hampden | 33 MW | 7.1 GWh | 3% | 1930 |
| New England Wind LLC | Wind | Berkshire | 29 MW | 74 GWh | 30% | 2012 |
| Outer Cape Community Battery | Storage | Barnstable | 25 MW | -0.1 GWh | – | 2022 |
| Boott Hydropower | Hydro | Middlesex | 23 MW | 61 GWh | 30% | 1985 |
| Nantucket Hybrid | Oil | Nantucket | 22 MW | -0.4 GWh | – | 2019 |
| Central Heating Plant | Natural gas | Hampshire | 20 MW | 80 GWh | 45% | 2007 |
| Berkshire Wind Power Project | Wind | Berkshire | 20 MW | 42 GWh | 24% | 2011 |
| NE Renewable Fitchburg, LLC | Biomass | Worcester | 18 MW | 79 GWh | 50% | 1992 |
| Deerfield 5 | Hydro | Berkshire | 18 MW | 44 GWh | 29% | 1974 |
| Univ of Massachusetts Medical Center | Natural gas | Worcester | 18 MW | 63 GWh | 41% | 1974 |
| Lawrence Hydroelectric Associates | Hydro | Essex | 15 MW | 59 GWh | 45% | 1981 |
| SJA Solar LLC-Solterra Monastery CSG | Solar | Worcester | 15 MW | 24 GWh | 18% | 2016 |
| Gillette SBMC | Natural gas | Suffolk | 14 MW | 55 GWh | 44% | 1971 |
| Shrewsbury | Oil | Worcester | 14 MW | 1.9 GWh | 2% | 1969 |
| Wellesley College Central Utility Plant | Natural gas | Norfolk | 14 MW | 9.6 GWh | 8% | 1985 |
| Cherry Street | Natural gas | Middlesex | 13 MW | 0.3 GWh | 0% | 1951 |
| Barrett PV | Solar | Worcester | 12 MW | 17 GWh | 17% | 2016 |
| Fife Brook | Hydro | Berkshire | 11 MW | 0.0 GWh | – | 1974 |
| High Street Station | Natural gas | Essex | 11 MW | 0.2 GWh | 0% | 1951 |
| West Water Street | Oil | Bristol | 10 MW | 2.4 GWh | 3% | 2018 |
| Blodgett Solar CSG | Solar | Middlesex | 10 MW | 9.3 GWh | 11% | 2021 |
| 59 Federal Rd(CSG) | Storage | Plymouth | 10 MW | 11 GWh | – | 2021 |
| Huxley Solar | Storage | Hampden | 10 MW | 10 GWh | – | 2022 |
| Beacon Solar, LLC | Storage | Hampshire | 10 MW | 7.8 GWh | – | 2022 |
| 0 Hammond St CSG | Storage | Plymouth | 9.8 MW | 14 GWh | – | 2021 |
| Old Middleboro Road Solar | Solar | Plymouth | 9.5 MW | 8.4 GWh | 10% | 2023 |
| Syncarpha Puddon I Hybrid CSG | Solar | Worcester | 9.0 MW | 8.4 GWh | 11% | 2021 |
| Syncarpha Puddon II Hybrid CSG | Solar | Worcester | 9.0 MW | 8.5 GWh | 11% | 2021 |
| Syncarpha Northbridge I Hybrid(CSG) | Solar | Worcester | 9.0 MW | 8.5 GWh | 11% | 2021 |
| Dunstable Solar 1, LLC | Storage | Middlesex | 9.0 MW | 8.4 GWh | – | 2021 |
| Syncarpha Millbury Hybrid (CSG) | Solar | Worcester | 8.8 MW | 8.0 GWh | 10% | 2022 |
| Syncarpha Blandford Hybrid CSG | Solar | Hampden | 8.8 MW | 7.9 GWh | 10% | 2019 |
| ASD Wallum MA Solar LLC(CSG) | Solar | Worcester | 8.8 MW | 8.7 GWh | 11% | 2022 |
| Auburn Solar Project | Solar | Worcester | 8.7 MW | 8.0 GWh | 11% | 2022 |
| Ryan Road Solar LLC Hybrid(CSG) | Storage | Worcester | 8.6 MW | 9.6 GWh | – | 2021 |
| West Haydenville PJ Community Solar | Solar | Hampshire | 8.6 MW | 8.6 GWh | 11% | 2022 |
| ZPD-PT Solar Project 2017-038 Hybrid LLC | Solar | Worcester | 8.5 MW | 7.5 GWh | 10% | 2021 |
| Happy Hollow CSG Hybrid | Solar | Worcester | 8.3 MW | 8.1 GWh | 11% | 2019 |
| Randall Solar Project Hybrid | Solar | Worcester | 8.3 MW | 8.5 GWh | 12% | 2021 |
| Williamsville Hybrid CSG | Solar | Worcester | 8.3 MW | 7.7 GWh | 11% | 2021 |
| Clark Road Solar 1, LLC | Solar | Worcester | 8.3 MW | 8.0 GWh | 11% | 2020 |
| 276 Federal Rd(CSG) | Solar | Plymouth | 8.3 MW | 9.4 GWh | 13% | 2021 |
| 160 Tihonet Rd Hybrid(CSG) | Solar | Plymouth | 8.3 MW | 9.9 GWh | 14% | 2021 |
| Adams Grove Solar | Solar | Berkshire | 8.3 MW | 6.0 GWh | 8% | 2022 |
| Front Street | Oil | Hampden | 8.1 MW | 1.2 GWh | 2% | 1978 |
| East Brookfield Adams Road Solar LLC CSG | Solar | Worcester | 8.1 MW | 7.4 GWh | 10% | 2021 |
| UMass Boston | Oil | Suffolk | 8.1 MW | 1.0 GWh | 1% | 1972 |
| Future Generation Wind | Wind | Plymouth | 8.0 MW | 11 GWh | 16% | 2016 |
| Syncarpha Northbridge II Hybrid CSG | Solar | Worcester | 8.0 MW | 7.6 GWh | 11% | 2021 |
| Middleton Solar Park | Solar | Essex | 8.0 MW | 6.6 GWh | 9% | 2018 |
| Brookwood Drive Community Solar | Solar | Bristol | 8.0 MW | 5.5 GWh | 8% | 2022 |
| Marston Mills Solar | Solar | Barnstable | 8.0 MW | 6.3 GWh | 9% | 2021 |
| NL MA - Copicut | Solar | Bristol | 8.0 MW | 6.1 GWh | – | 2025 |
| BWC Lake Lashaway, LLC Hybrid | Solar | Worcester | 7.9 MW | 8.2 GWh | 12% | 2021 |
| Ameresco Chicopee Energy | Biomass | Hampden | 7.8 MW | 3.7 GWh | 5% | 2004 |
| Annese Solar Project Hybrid CSG | Solar | Worcester | 7.8 MW | 7.9 GWh | 12% | 2020 |
| Amaterasu LLC | Solar | Worcester | 7.8 MW | 7.0 GWh | 10% | 2021 |
| Mt. Tom Solar Project Hybrid | Solar | Hampden | 7.6 MW | 4.2 GWh | 6% | 2017 |
| Syncarpha Westminster Hybrid CSG | Solar | Worcester | 7.6 MW | 5.7 GWh | 9% | 2022 |
| Partridge Solar | Solar | Berkshire | 7.5 MW | 8.1 GWh | 12% | 2022 |
| Skyline Solar | Solar | Berkshire | 7.5 MW | 8.2 GWh | 13% | 2022 |
| McDougle-Mitchell Solar Project Hybrid C | Solar | Worcester | 7.4 MW | 6.9 GWh | 11% | 2020 |
Coming next
Planned projects
The largest generators reported as planned in Massachusetts, by expected year. Plans change; some will be delayed or cancelled.
| Project | Source | County | Capacity | Expected |
|---|---|---|---|---|
| Energizar BESS | Storage | Suffolk | 250 MW | 2027 |
| Taft BESS | Storage | Worcester | 200 MW | 2027 |
| Salt Cod BESS | Storage | Bristol | 168 MW | 2028 |
| Town of Sharon Portfolio -Mt St Landfill | Storage | Norfolk | 5.7 MW | 2027 |
| Sturbridge Road Solar | Solar | Worcester | 5.0 MW | 2026 |
| Holyoke MA BESS 1 | Storage | Hampden | 5.0 MW | 2026 |
| Chicopee BESS | Storage | Hampden | 5.0 MW | 2026 |
| Framingham BESS | Storage | Middlesex | 5.0 MW | 2026 |
| Borrego - Highland Ave | Solar | Bristol | 5.0 MW | 2026 |
| Borrego - Highland Ave | Storage | Bristol | 5.0 MW | 2026 |
| Ipswich MA BESS 1 | Storage | Essex | 5.0 MW | 2026 |
| Town of Sharon Portfolio -Mt St Landfill | Solar | Norfolk | 5.0 MW | 2027 |
| Braley Hill North Solar | Storage | Plymouth | 5.0 MW | 2027 |
| Braley Hill North Solar | Solar | Plymouth | 5.0 MW | 2027 |
| Randall Lane Solar | Storage | Plymouth | 5.0 MW | 2027 |
| Randall Lane Solar | Solar | Plymouth | 5.0 MW | 2027 |
| Clems Way Solar | Solar | Bristol | 5.0 MW | 2027 |
| Logging Swamp North | Solar | Plymouth | 5.0 MW | 2027 |
| Logging Swamp South | Solar | Plymouth | 5.0 MW | 2027 |
| Snipatuit Road Solar | Storage | Plymouth | 4.0 MW | 2027 |
| Snipatuit Road Solar | Solar | Plymouth | 4.0 MW | 2027 |
| MA Acushnet 540R Main St | Solar | Bristol | 4.0 MW | 2027 |
| Cushman Road Solar | Storage | Plymouth | 3.0 MW | 2027 |
| Cushman Road Solar | Solar | Plymouth | 3.0 MW | 2027 |
| Belchertown Solar PV + Battery Project | Solar | Hampshire | 2.8 MW | 2026 |
| Belchertown Solar PV + Battery Project | Storage | Hampshire | 2.8 MW | 2026 |
| Solar Carver 1 Hybrid | Storage | Plymouth | 2.0 MW | 2026 |
| Solar Carver 1 Hybrid | Solar | Plymouth | 2.0 MW | 2026 |
| MA Acushnet 540R Main St | Storage | Bristol | 2.0 MW | 2027 |
| Solar Carver 3 Hybrid | Storage | Plymouth | 1.0 MW | 2026 |
Shut down
Retired since 2010
The largest generators retired in Massachusetts since 2010.
| Plant | Source | Capacity | Retired |
|---|---|---|---|
| Pilgrim Nuclear Power Station | Nuclear | 670 MW | 2019 |
| Brayton Point | Coal | 643 MW | 2017 |
| Mystic Generating Station | Oil | 617 MW | 2021 |
| Brayton Point | Oil | 476 MW | 2017 |
| Salem Harbor | Oil | 476 MW | 2014 |
| Mystic Generating Station | Natural gas | 315 MW | 2024 |
| Mystic Generating Station | Natural gas | 315 MW | 2024 |
| Mystic Generating Station | Natural gas | 279 MW | 2024 |
| Mystic Generating Station | Natural gas | 279 MW | 2024 |
| Mystic Generating Station | Natural gas | 279 MW | 2024 |
| Mystic Generating Station | Natural gas | 279 MW | 2024 |
| Brayton Point | Coal | 241 MW | 2017 |
| Brayton Point | Coal | 241 MW | 2017 |
| Salem Harbor | Coal | 166 MW | 2014 |
| Mount Tom | Coal | 136 MW | 2014 |
| Essential Power Massachusetts LLC | Natural gas | 114 MW | 2021 |
| Somerset Station | Coal | 100 MW | 2011 |
| Salem Harbor | Coal | 82 MW | 2014 |
| Salem Harbor | Coal | 82 MW | 2014 |
| Potter Station 2 | Natural gas | 76 MW | 2024 |
| Essential Power Massachusetts LLC | Natural gas | 60 MW | 2022 |
| Essential Power Massachusetts LLC | Natural gas | 60 MW | 2022 |
| Tanner Street Generation | Natural gas | 58 MW | 2024 |
| Cleary Flood Hybrid | Oil | 28 MW | 2020 |
| Tanner Street Generation | Natural gas | 27 MW | 2024 |
| Potter Station 2 | Natural gas | 25 MW | 2024 |
| Lowell Cogeneration Company LP | Natural gas | 25 MW | 2013 |
| Somerset Station | Oil | 25 MW | 2011 |
| Kendall Square Station | Natural gas | 23 MW | 2018 |
| Waters River | Natural gas | 21 MW | 2026 |
Sources: U.S. Energy Information Administration: state historical generation tables (1990–2025), Form EIA-860M generator inventory (September 2026) and Form EIA-923 plant generation. Shares leave out pumped storage. Rooftop solar is not included. Methodology.