Storage power plant · Grimes, TX
Blue Jay Solar I, LLC
Blue Jay Solar I, LLC is a 52 MW storage power plant in Grimes County, Texas, operated by Blue Jay Solar I, LLC. Its oldest generator still running came online in 2023. In 2025 it generated 444 GWh, about what 33,000 average Texas homes use in a year.
Blue Jay Solar I, LLC in context
Among the 233 storage plants in Texas in the EIA's inventory, it is the 93rd largest, about 0.3% of the state's 16 GW of storage capacity.
Grimes County has 4 power plants of 1 MW or more with 1.3 GW in all; Blue Jay Solar I, LLC is 4% of that and the 2nd largest of 2 storage plants there.
The average electricity customer in Grimes County goes 9.4 hours a year without power, the 126th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923. Storage uses more energy charging than it returns, so its net figure is negative.
Where it is
Blue Jay Solar I, LLC (outlined) and other plants in Grimes County, shaded. 30.705, -96.070.
Plant facts
- Operator
- Blue Jay Solar I, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Grimes County, TX
- EIA plant ID
- 64672
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| BLUEJ | Batteries | 52 MW · 85 MWh | 2023 | – |
Planned
| Generator | Technology | Capacity | Expected |
|---|---|---|---|
| BLUJS | Solar Photovoltaic | 210 MW | 2026 |
Nearby
Other plants in Grimes County
Questions
Blue Jay Solar I, LLC, answered
How much can Blue Jay Solar I, LLC store and deliver?
Blue Jay Solar I, LLC can deliver up to 52 MW and hold 85 MWh of energy, from one battery or storage system. Its net energy in 2025 was 444 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.
Where is Blue Jay Solar I, LLC?
Blue Jay Solar I, LLC is in Grimes County, Texas, at about 30.705°, -96.070°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Grimes County goes 9.4 hours a year without power, the 126th most of 240 counties in Texas. The county's page has the full outage record.
Who operates Blue Jay Solar I, LLC?
It is operated by Blue Jay Solar I, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Blue Jay Solar I, LLC open?
Its oldest generator still running came online in 2023. 1 more generator is planned.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2023–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.