Storage power plant · Grimes, TX
TX15 Limousin Oak Storage
TX15 Limousin Oak Storage is a 100 MW storage power plant in Grimes County, Texas, operated by Key Capture Energy. Its oldest generator still running came online in 2024.
TX15 Limousin Oak Storage in context
Among the 233 storage plants in Texas in the EIA's inventory, it is the 74th largest, about 0.6% of the state's 16 GW of storage capacity.
Grimes County has 4 power plants of 1 MW or more with 1.3 GW in all; TX15 Limousin Oak Storage is 8% of that and the largest of 2 storage plants there.
The average electricity customer in Grimes County goes 9.4 hours a year without power, the 126th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923. Storage uses more energy charging than it returns, so its net figure is negative.
Where it is
TX15 Limousin Oak Storage (outlined) and other plants in Grimes County, shaded. 30.660, -95.974.
Plant facts
- Operator
- Key Capture Energy
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Grimes County, TX
- EIA plant ID
- 65698
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| TX15 | Batteries | 100 MW · 227 MWh | 2024 | – |
Nearby
Other plants in Grimes County
Questions
TX15 Limousin Oak Storage, answered
How much can TX15 Limousin Oak Storage store and deliver?
TX15 Limousin Oak Storage can deliver up to 100 MW and hold 227 MWh of energy, from one battery or storage system. Its net energy in 2025 was -14.8 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.
Where is TX15 Limousin Oak Storage?
TX15 Limousin Oak Storage is in Grimes County, Texas, at about 30.660°, -95.974°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Grimes County goes 9.4 hours a year without power, the 126th most of 240 counties in Texas. The county's page has the full outage record.
Who operates TX15 Limousin Oak Storage?
It is operated by Key Capture Energy (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did TX15 Limousin Oak Storage open?
Its oldest generator still running came online in 2024.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2024–2025). Methodology.