Solar power plant · Torrance, NM

Britton Solar Energy Center

Britton Solar Energy Center is a 50 MW solar power plant in Torrance County, New Mexico, operated by Exus New Mexico. Its oldest generator still running came online in 2019. In 2025 it generated 141 GWh, about what 18,000 average New Mexico homes use in a year.

Capacity50 MWNameplate, September 2026
Generated141 GWhIn 2025
Capacity factor32%Share of the most it could make, 2025
Generators1Oldest from 2019

Britton Solar Energy Center in context

Among the 111 solar plants in New Mexico in the EIA's inventory, it is the 18th largest, about 1.3% of the state's 3.8 GW of solar capacity.

Torrance County has 7 power plants of 1 MW or more with 2.2 GW in all; Britton Solar Energy Center is 2% of that and the largest of 2 solar plants there.

Its capacity factor of 32% in 2025 is higher than the 20% typical for solar plants across the US.

The average electricity customer in Torrance County goes 11 hours a year without power, the 2nd most of 20 counties in New Mexico. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

0501001502002019202020212022202320242025GWh 141
0501001502002019202120232025141

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Britton Solar Energy Center (outlined) and other plants in Torrance County, shaded. 35.016, -106.098.

Plant facts

Operator
Exus New Mexico
Sector
IPP Non-CHP
Grid operator
PNM
County
Torrance County, NM
EIA plant ID
63579
Where New Mexico's power comes from → New Mexico power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
BSEC Solar Photovoltaic 50 MW 2019 –

Questions

Britton Solar Energy Center, answered

How much power does Britton Solar Energy Center produce?

Britton Solar Energy Center has 50 MW of capacity from one generator. In 2025 it generated 141 GWh, 32% of the most it could have made running flat out all year (its capacity factor).

How many homes does Britton Solar Energy Center power?

Its 2025 output of 141 GWh equals the yearly electricity use of about 18,000 average New Mexico homes (638 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Britton Solar Energy Center?

Britton Solar Energy Center is in Torrance County, New Mexico, at about 35.016°, -106.098°. It is one of 7 power plants of 1 MW or more in the county. The average electricity customer in Torrance County goes 11 hours a year without power, the 2nd most of 20 counties in New Mexico. The county's page has the full outage record.

Who operates Britton Solar Energy Center?

It is operated by Exus New Mexico (EIA sector: IPP Non-CHP), and it feeds balancing authority PNM.

When did Britton Solar Energy Center open?

Its oldest generator still running came online in 2019.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2019–2025). Homes equivalent uses the average New Mexico home's 638 kWh a month in 2025. Methodology.