Biomass power plant · Glynn, GA

Brunswick Cellulose

Brunswick Cellulose is a 72 MW biomass power plant in Glynn County, Georgia, operated by Brunswick Cellulose LLC. Its oldest generator still running came online in 1954. In 2025 it generated 217 GWh, about what 17,000 average Georgia homes use in a year.

Capacity72 MWNameplate, September 2026
Generated217 GWhIn 2025
Capacity factor34%Share of the most it could make, 2025
Generators3Oldest from 1954

Brunswick Cellulose in context

Among the 46 other-fuel plants in Georgia in the EIA's inventory, it is the 10th largest, about 3.1% of the state's 2.3 GW of other-fuel capacity.

Glynn County has 3 power plants of 1 MW or more with 650 MW in all; Brunswick Cellulose is 11% of that and the 2nd largest of 2 biomass plants there.

Its capacity factor of 34% in 2025 is higher than the 25% typical for biomass plants across the US.

The average electricity customer in Glynn County goes 15 hours a year without power, the 47th most of 156 counties in Georgia. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

020040060020182019202020212022202320242025GWh 217
02004006002019202120232025217

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Brunswick Cellulose (outlined) and other plants in Glynn County, shaded. 31.173, -81.519.

Plant facts

Operator
Brunswick Cellulose LLC
Sector
Industrial CHP
Grid operator
SOCO
County
Glynn County, GA
EIA plant ID
10605
Where Georgia's power comes from → Georgia power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
GEN4 Wood/Wood Waste Biomass 50 MW 1960 –
GEN5 Wood/Wood Waste Biomass 13 MW 1996 –
GEN3 Wood/Wood Waste Biomass 9.2 MW 1954 –

Nearby

Other plants in Glynn County

Questions

Brunswick Cellulose, answered

How much power does Brunswick Cellulose produce?

Brunswick Cellulose has 72 MW of capacity from 3 generators. In 2025 it generated 217 GWh, 34% of the most it could have made running flat out all year (its capacity factor).

How many homes does Brunswick Cellulose power?

Its 2025 output of 217 GWh equals the yearly electricity use of about 17,000 average Georgia homes (1,077 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Brunswick Cellulose?

Brunswick Cellulose is in Glynn County, Georgia, at about 31.173°, -81.519°. It is one of 3 power plants of 1 MW or more in the county. The average electricity customer in Glynn County goes 15 hours a year without power, the 47th most of 156 counties in Georgia. The county's page has the full outage record.

Who operates Brunswick Cellulose?

It is operated by Brunswick Cellulose LLC (EIA sector: Industrial CHP), and it feeds Southern Company.

When did Brunswick Cellulose open?

Its oldest generator still running came online in 1954.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Georgia home's 1,077 kWh a month in 2025. Methodology.