Storage power plant · Brazoria, TX
Byrd Ranch Storage
Byrd Ranch Storage is a 50 MW storage power plant in Brazoria County, Texas, operated by Byrd Ranch Storage LLC. Its oldest generator still running came online in 2022.
Byrd Ranch Storage in context
Among the 233 storage plants in Texas in the EIA's inventory, it is the 94th largest, about 0.3% of the state's 16 GW of storage capacity.
Brazoria County has 42 power plants of 1 MW or more with 6.1 GW in all; Byrd Ranch Storage is 1% of that and the 10th largest of 19 storage plants there.
The average electricity customer in Brazoria County goes 28 hours a year without power, the 19th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923. Storage uses more energy charging than it returns, so its net figure is negative.
Where it is
Byrd Ranch Storage (outlined) and other plants in Brazoria County, shaded. 29.056, -95.686.
Plant facts
- Operator
- Byrd Ranch Storage LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Brazoria County, TX
- EIA plant ID
- 65259
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| P1 | Batteries | 50 MW · 50 MWh | 2022 | – |
Questions
Byrd Ranch Storage, answered
How much can Byrd Ranch Storage store and deliver?
Byrd Ranch Storage can deliver up to 50 MW and hold 50 MWh of energy, from one battery or storage system. Its net energy in 2025 was -4.2 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.
Where is Byrd Ranch Storage?
Byrd Ranch Storage is in Brazoria County, Texas, at about 29.056°, -95.686°. It is one of 42 power plants of 1 MW or more in the county. The average electricity customer in Brazoria County goes 28 hours a year without power, the 19th most of 240 counties in Texas. The county's page has the full outage record.
Who operates Byrd Ranch Storage?
It is operated by Byrd Ranch Storage LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Byrd Ranch Storage open?
Its oldest generator still running came online in 2022.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2023–2025). Methodology.