Wind power plant · Quay, NM
Caprock Wind Farm
Caprock Wind Farm is a 100 MW wind power plant in Quay County, New Mexico, operated by Leeward Asset Management, LLC. Its oldest generator still running came online in 2004. In 2025 it generated 379 GWh, about what 49,000 average New Mexico homes use in a year.
Caprock Wind Farm in context
Among the 31 wind plants in New Mexico in the EIA's inventory, it is the 19th largest, about 1.2% of the state's 8.1 GW of wind capacity.
Quay County has 6 power plants of 1 MW or more with 409 MW in all; Caprock Wind Farm is 24% of that and the 2nd largest of 4 wind plants there.
Its capacity factor of 43% in 2025 is higher than the 32% typical for wind plants across the US.
The average electricity customer in Quay County goes 3.4 hours a year without power, the 11th most of 20 counties in New Mexico. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Caprock Wind Farm (outlined) and other plants in Quay County, shaded. 34.981, -103.354.
Plant facts
- Operator
- Leeward Asset Management, LLC
- Sector
- IPP Non-CHP
- Grid operator
- SWPP
- County
- Quay County, NM
- EIA plant ID
- 56293
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Onshore Wind Turbine | 80 MW | 2004 | – |
| 2 | Onshore Wind Turbine | 20 MW | 2005 | – |
Nearby
Other plants in Quay County
Questions
Caprock Wind Farm, answered
How much power does Caprock Wind Farm produce?
Caprock Wind Farm has 100 MW of capacity from 2 generators. In 2025 it generated 379 GWh, 43% of the most it could have made running flat out all year (its capacity factor).
How many homes does Caprock Wind Farm power?
Its 2025 output of 379 GWh equals the yearly electricity use of about 49,000 average New Mexico homes (638 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Caprock Wind Farm?
Caprock Wind Farm is in Quay County, New Mexico, at about 34.981°, -103.354°. It is one of 6 power plants of 1 MW or more in the county. The average electricity customer in Quay County goes 3.4 hours a year without power, the 11th most of 20 counties in New Mexico. The county's page has the full outage record.
Who operates Caprock Wind Farm?
It is operated by Leeward Asset Management, LLC (EIA sector: IPP Non-CHP), and it feeds the Southwest Power Pool.
When did Caprock Wind Farm open?
Its oldest generator still running came online in 2004.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average New Mexico home's 638 kWh a month in 2025. Methodology.