Wind power plant · Lincoln, CO

Cedar Point Wind

Cedar Point Wind is a 252 MW wind power plant in Lincoln County, Colorado, operated by Cedar Point LLC. Its oldest generator still running came online in 2011. In 2025 it generated 693 GWh, about what 88,000 average Colorado homes use in a year.

Capacity252 MWNameplate, September 2026
Generated693 GWhIn 2025
Capacity factor31%Share of the most it could make, 2025
Generators1Oldest from 2011

Cedar Point Wind in context

Among the 34 wind plants in Colorado in the EIA's inventory, it is the 6th largest, about 4.3% of the state's 5.9 GW of wind capacity.

Lincoln County has 5 power plants of 1 MW or more with 1.0 GW in all; Cedar Point Wind is 25% of that and the largest of 4 wind plants there.

Its capacity factor of 31% in 2025 is close to the 32% typical for wind plants across the US.

The average electricity customer in Lincoln County goes 2.8 hours a year without power, the 24th most of 39 counties in Colorado. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

020040060080020182019202020212022202320242025GWh 693
02004006008002019202120232025693

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Cedar Point Wind (outlined) and other plants in Lincoln County, shaded. 39.422, -103.678.

Plant facts

Operator
Cedar Point LLC
Sector
IPP Non-CHP
Grid operator
PSCO
County
Lincoln County, CO
EIA plant ID
57315
Where Colorado's power comes from → Colorado power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1-139 Onshore Wind Turbine 252 MW 2011 –

Questions

Cedar Point Wind, answered

How much power does Cedar Point Wind produce?

Cedar Point Wind has 252 MW of capacity from one generator. In 2025 it generated 693 GWh, 31% of the most it could have made running flat out all year (its capacity factor).

How many homes does Cedar Point Wind power?

Its 2025 output of 693 GWh equals the yearly electricity use of about 88,000 average Colorado homes (658 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Cedar Point Wind?

Cedar Point Wind is in Lincoln County, Colorado, at about 39.422°, -103.678°. It is one of 5 power plants of 1 MW or more in the county. The average electricity customer in Lincoln County goes 2.8 hours a year without power, the 24th most of 39 counties in Colorado. The county's page has the full outage record.

Who operates Cedar Point Wind?

It is operated by Cedar Point LLC (EIA sector: IPP Non-CHP), and it feeds Public Service Company of Colorado.

When did Cedar Point Wind open?

Its oldest generator still running came online in 2011.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Colorado home's 658 kWh a month in 2025. Methodology.