Storage power plant · Yavapai, AZ
Chino Valley Solar
Chino Valley Solar is a 38 MW storage power plant in Yavapai County, Arizona, operated by Arizona Public Service Co. Its oldest generator still running came online in 2012. In 2025 it generated 33 GWh, about what 2,700 average Arizona homes use in a year.
Chino Valley Solar in context
Among the 41 storage plants in Arizona in the EIA's inventory, it is the 33rd largest, about 0.6% of the state's 6.3 GW of storage capacity.
Yavapai County has 4 power plants of 1 MW or more with 67 MW in all; Chino Valley Solar is 57% of that.
The average electricity customer in Yavapai County goes 3.0 hours a year without power, the 3rd most of 11 counties in Arizona. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923. Storage uses more energy charging than it returns, so its net figure is negative.
Where it is
Chino Valley Solar (outlined) and other plants in Yavapai County, shaded. 34.718, -112.429.
Plant facts
- Operator
- Arizona Public Service Co
- Sector
- Electric Utility
- Grid operator
- AZPS
- County
- Yavapai County, AZ
- EIA plant ID
- 57560
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| PV1 | Solar Photovoltaic | 19 MW | 2012 | – |
| CV19M | Batteries | 19 MW · 76 MWh | 2024 | – |
Nearby
Other plants in Yavapai County
Questions
Chino Valley Solar, answered
How much can Chino Valley Solar store and deliver?
Chino Valley Solar can deliver up to 38 MW and hold 76 MWh of energy, from 2 storage units. Its net energy in 2025 was 33 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.
Where is Chino Valley Solar?
Chino Valley Solar is in Yavapai County, Arizona, at about 34.718°, -112.429°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Yavapai County goes 3.0 hours a year without power, the 3rd most of 11 counties in Arizona. The county's page has the full outage record.
Who operates Chino Valley Solar?
It is operated by Arizona Public Service Co (EIA sector: Electric Utility), and it feeds Arizona Public Service.
When did Chino Valley Solar open?
Its oldest generator still running came online in 2012.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Arizona home's 1,030 kWh a month in 2025. Methodology.