Storage power plant · San Diego, CA
Clairemont Energy Storage
Clairemont Energy Storage is a 10 MW storage power plant in San Diego County, California, operated by San Diego Gas & Electric Co. Its oldest generator still running came online in 2024.
Clairemont Energy Storage in context
Among the 156 storage plants in California in the EIA's inventory, it is the 107th largest, about 0.1% of the state's 13 GW of storage capacity.
San Diego County has 107 power plants of 1 MW or more with 5.1 GW in all; Clairemont Energy Storage is 0% of that and the 20th largest of 33 storage plants there.
The average electricity customer in San Diego County goes 3.3 hours a year without power, the 49th most of 56 counties in California. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923. Storage uses more energy charging than it returns, so its net figure is negative.
Where it is
Clairemont Energy Storage (outlined) and other plants in San Diego County, shaded. 32.826, -117.183.
Plant facts
- Operator
- San Diego Gas & Electric Co
- Sector
- Electric Utility
- Grid operator
- CISO
- County
- San Diego County, CA
- EIA plant ID
- 66266
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Batteries | 10 MW · 10 MWh | 2024 | – |
Questions
Clairemont Energy Storage, answered
How much can Clairemont Energy Storage store and deliver?
Clairemont Energy Storage can deliver up to 10 MW and hold 10 MWh of energy, from one battery or storage system. Its net energy in 2025 was -1.3 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.
Where is Clairemont Energy Storage?
Clairemont Energy Storage is in San Diego County, California, at about 32.826°, -117.183°. It is one of 107 power plants of 1 MW or more in the county. The average electricity customer in San Diego County goes 3.3 hours a year without power, the 49th most of 56 counties in California. The county's page has the full outage record.
Who operates Clairemont Energy Storage?
It is operated by San Diego Gas & Electric Co (EIA sector: Electric Utility), and it feeds the California ISO.
When did Clairemont Energy Storage open?
Its oldest generator still running came online in 2024.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2024–2025). Methodology.